how to calculate the volume of water in the water tank
(5'x5'x5')? what"s the formula?
Answers were Sorted based on User's Feedback
Answer / deepak
1 cft = 28.37 litres of water.
So 125 cft of tank can handle 3546.25 litres of water.
Is This Answer Correct ? | 377 Yes | 52 No |
Answer / bert05
one cubic meter is equal to 35.315 cubic feet. so one cubic
feet = 1/35.315 cubic meter = 0.0283 cubic meter
L=5'
w=5'
h=5'
V=L*W*H
=5'*5'*5'
=125 Cubic feet
125*0.0283
=3,538 cubic meter
=3,538 litres volume of water in the tank
Is This Answer Correct ? | 284 Yes | 68 No |
Answer / bala
Take the internal diemention of the tank with the present
depth of water in meters and derive the volume(cu.m} then
multiply by 1000 to get the result in litres.
To know the actual capacity of a tank measure the depth
form the base to the sill of overflow sleeve and calculate.
Is This Answer Correct ? | 168 Yes | 41 No |
Answer / bangaru babu
calculate the water tank volume in cuft.
1cuft = 28.32 liters
example : if u got the volume of water tank is 200cuft
then vol of water = 28.32 x 200 = 5664 liters
From the above u can understand that for every 100 cuft volume nearly 2832 liters of water is stored.
Is This Answer Correct ? | 98 Yes | 32 No |
Answer / akbar_u2u
Lenght=5'
Breadth=5'
Height=5'
Formula to be used..
volum=Lenght*Breadth*Height
volume=5'*5'*5'
volume=125cft
Is This Answer Correct ? | 91 Yes | 30 No |
Answer / sachin kesarkar
assuming free board=150mm=.5feet
hence height=4.5feets
now total volume=5*5*4.5=112.5cubic feet
hence112.5/35.28=3.18cubic metres
now 1metre cube=1000litres
hence 3.18*1000=3180litres
Is This Answer Correct ? | 54 Yes | 22 No |
Answer / santosh
volume is calculated as
1)for circular tank
v = 3.412/4 X d2 x height of tank
2) for rectangular tank
v = l x b x h
Is This Answer Correct ? | 44 Yes | 21 No |
Answer / anil
one cubic meter is equal to 35.315 cubic feet. so one cubic
feet = 1/35.315 cubic meter = 0.0283 cubic meter
L=5'
w=5'
h=5'
V=L*W*H
=5'*5'*5'
=125 Cubic feet
125*0.0283
=3,538 cubic meter
=3,538 litres volume of water in the tank
Is This Answer Correct ? 38 Yes 4 No
Bert05
Answer
# 4 5'X5'X5'=125cu.ft
Is This Answer Correct ? 54 Yes 23 No
Sri
Answer
# 5 calculate the water tank volume in cuft.
1cuft = 28.32 liters
example : if u got the volume of water tank is 200cuft
then vol of water = 28.32 x 200 = 5664 liters
From the above u can understand that for every 100 cuft volume nearly 2832 liters of water is stored.
Is This Answer Correct ? 33 Yes 11 No
Bangaru Babu
Answer
# 6 Lenght=5'
Breadth=5'
Height=5'
Formula to be used..
volum=Lenght*Breadth*Height
volume=5'*5'*5'
volume=125cft
Thanks for Marking this Answer
Akbar_u2u
Answer
# 7 assuming free board=150mm=.5feet
hence height=4.5feets
now total volume=5*5*4.5=112.5cubic feet
hence112.5/35.28=3.18cubic metres
now 1metre cube=1000litres
hence 3.18*1000=3180litres
Is This Answer Correct ? 22 Yes 8 No
Sachin Kesarkar
Answer
# 8 125.000 Cubic Feet = 3,539.606 Litres
Is This Answer Correct ? 16 Yes 5 No
Prashankumar
Answer
# 9 volume is calculated as
1)for circular tank
v = 3.412/4 X d2 x height of tank
2) for rectangular tank
v = l x b x h
Is This Answer Correct ? | 17 Yes | 7 No |
what is the density of steel and concrete in kg/m3?
1)What is swear, swage and storm water? 2)What are the sizes of bricks based on Nominal, practical and standard? 3) What is the distinguies between the grade of cement 43, 53?
50m3 concrete volume how much cement sand aggregate details radio m20grade
5 Answers L&T, Mars Planning Engineering Services, Relcon Infraprojects,
What is the Unit weight of coarse sand (F.M- 2.20) ?????
How much is the cover for slab?
Any bopdy tell me how to prepare rate analysis for Centering and shuttering for RAFT FOUNDATION, SUSPENDED FLOORS, STAIR CASES, RETAINING WALLS, SHEAR WALL and COLUMNS
Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.
what is the standard size of brick available in site in mm
How to Calculate no.of bricks in 1sq.mtr
what is the difference between the splice & Lap length.
when will the position neutral axis shifted in beams
FOR concrete structure curing is important for hydration process,curing component is good for the concrete if W/C ratio is more than .38