how to calculate Tile skirting
Answers were Sorted based on User's Feedback
Answer / akrmsb
It is done by the formula 2(l+B)-deductions.
For example length of the room is 5 mts
and breath is 4 mts
then the qauntity of skirting will be 2(4+5)= 18mts.
from this subtract the deductions like doors.
if the width of the door is 1.2 mts then the final quantity will be 18-1.2=16.8 mts.
| Is This Answer Correct ? | 101 Yes | 23 No |
above answer is correct. it is always calculate in rmt.
| Is This Answer Correct ? | 34 Yes | 8 No |
Answer / akash choudhary
Yes it is absolutely correct it is measured in running meters(rmt)
| Is This Answer Correct ? | 17 Yes | 3 No |
Answer / madhu
If you need a quantifier of tiles you should measure the length with measuring tape of skirting tile
For Eg: A house is having 200rft length skirting tile and tile size is 2ft *2ft, keeping 4inch as skirting tile width we get 6tiles from 1 tile so that formula is
Total rft of skirting tile / (1 tile length* No of skirting tiles from 1tile)=No of tiles
200rft/(2ft*6No)=16.667~17 no of tiles required
Eg 2: if tile size is 2ft*4ft for the same 200rft
from 1 tile we get 6 skirting tile keeping 4ft as length
200rft/(4ft*6No)=8.334~9 no of tiles required
In site conditions, 2ft*4ft tile comes in 2no in a box so that we mention as 4box and 1 piece required for skirting tiles excluding wastage percentage
| Is This Answer Correct ? | 6 Yes | 0 No |
how to absorb to site basic corrections? which are the important correction?
How about the temperature of grade 35A concrete? Does it depend on the ambient temperature?
What is Bearing Capacity of Soil? How will you calculate for a particular type of Soil?
5 Answers Nagarjuna Construction,
waht is the range of compacting factor test result for good concreate?
how to take out quantity of steel used in column and beam?? what is standard formula for it???
plz send me civil q papers of hpcl
Brick size ? & 1 square feet brick work for use brick
Allowable wastage for ready mix concrete?
1cracks found in brick wall in service building, how to rectify it,with low cost ? how to find propagation of cracks (in depthwise) and arrest on that stage? Is it require to design for Expansion joint in Brick work? if so what is the required distaces?
what is Short bored pile foundation.
what are the differences between Tie beam, Ground beam and strap beam. thanks
Mujhe koi ye bta do ki 1.54 hi ku lete h material ki quantity niklne ke liye Sab jgha dhund liya bt samj nhi aaya mujhe koi alag aalag krke smjao ki cement m aggr. Dust m itne % wet or dry % hoti h fir kaise kaise 1.54 aaya kha se aaya smjao koi pls m confuse hu my calling nd wts app no. Is +919034604938
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)