For m25 1:1:2
How to get the quantities of cement,sand,agg for 1cu.mt.
thnks in advnce
Answer / ranjithkumar.t
M25 = 1:1:2 ( for 1 M^3 )
ingredient value of 40mm- 1.52
if you use 40mm aggregate otherwise 20mm aggregate ingredient value is 1.56
cement =1/4*1.52*28.8
= 10.94 bags => say 11 bags
Sand = 1/4*1.52
= 0.38 cubic meter => say 13.4 CFT
Aggregate = 2/4*1.52
= 0.76 cubic meter => say 26.8 CFT
| Is This Answer Correct ? | 6 Yes | 1 No |
contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?
how to start basic designing in structure..procedure to knw basic start to do structural designs in civil field?
What is creep ,deflection and shrinkage in concrete
why wire mesh is used in plastering
How much steel required in 900 square feet slab?
17 Answers RCC, Sai Steel Corporation, TATA,
What are your future hopes for this job?
Any strength is a stress but any stress is not strength
What are the alternate material for steel, Sand and aggregate
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
what is permissible IRC limits of silt content in river sand in India
How to calculate the crank rod in slab
0 Answers Bridge and Roof, Krishna Constructions,
Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)