Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


For m25 1:1:2
How to get the quantities of cement,sand,agg for 1cu.mt.
thnks in advnce



For m25 1:1:2 How to get the quantities of cement,sand,agg for 1cu.mt. thnks in advnce..

Answer / ranjithkumar.t

 M25 = 1:1:2 ( for 1 M^3 )
ingredient value of 40mm- 1.52 

if you use 40mm aggregate otherwise 20mm aggregate ingredient value is 1.56

  cement  =1/4*1.52*28.8
          = 10.94 bags => say 11 bags
   
  Sand   = 1/4*1.52
         = 0.38 cubic meter => say 13.4 CFT

Aggregate = 2/4*1.52
          = 0.76 cubic meter => say 26.8 CFT

Is This Answer Correct ?    6 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

how many express way in india

1 Answers   DVC,


how to mack bbs

1 Answers  


How much quantity of Cement and Sand required for Cement Sand Ratio of 1:1 and volume of pile is 0.61 m3

5 Answers  


20 mpa what is the quantity of cement sand and aggregate in one cubic meter of pcc non rainforcement concreate kindly answer including formaula thanks

0 Answers  


how to carry out rate analysis for RCC work in column using M20 ?

1 Answers   Mazna Building Contracting,


whats is difference between anchorage length and development length

0 Answers  


The resultant upthrust on a body partially immersed in a liquid acts through?

5 Answers   TNPSC Tamil Nadu Public Service Commission,


How to calculate the length of chairs provided to support the top rebar in concrete foundation

2 Answers   L&T, TCE,


What was asked in isro civil interview

0 Answers  


What is cement-concrete ratio ?

4 Answers  


minimum thickness of pcc 1;4;8 for road concrete

1 Answers  


How many jacks and props required for one floor, or tell me any thumbrule...to know the approx jacks and props required.?

1 Answers   Sumadhura Infracon,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)