if compressive strength on 28day pass, and client is asking
core test. is there any thing in standards allows that??
Answer / ramesh potaraju
if compressive strength on 28 day pass.
but that will not reached TARGET MEAN STRENGTH .
That's why client is asking for core testing
| Is This Answer Correct ? | 4 Yes | 0 No |
what is the difference between lap length & development length of reinforcement steel bars
1 Answers APGenco, Consolidated Construction Consortium Limited,
What are the Tests required to check the Quality of bar?
How is improve my knowledge in construction industries....
How to calculate chejja reinforcement
What is the weight of std brick and 6" ,8",4" solid block...?
I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shuttering?
what is difference between bending and twisting
what will happen if we pass electric current through rebars of RCC Slab(is there any strength reduction of concrete during this)??????????
2 Answers Precast, SPC Systems,
What are the advantages of Prestressed Concrete
What is the meaning of Fe415 ?
6 Answers Arul Constructions, L&T, SSM,
Adout concrete
how many no of light weight solid blocks of size 600x200x200mm required for 1cum of block work
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)