why we do pcc.?

Answers were Sorted based on User's Feedback



why we do pcc.?..

Answer / kdg

Plain Cement Concrete (PCC) is nothing but a layer between
reinforcement and soil/mud to protect reinforcement as well
as RCC from direct contact of soil/mud beneath the
foundation.

Is This Answer Correct ?    16 Yes 1 No

why we do pcc.?..

Answer / guest

this is the leveling coarse.

Is This Answer Correct ?    14 Yes 3 No

why we do pcc.?..

Answer / yogesh yadav

plain cement
concret is a
base structre of
building,its save
to
renforcement
direct contact
to mud soil.

Is This Answer Correct ?    5 Yes 0 No

why we do pcc.?..

Answer / suresh s sonone

1.To make the surface uniform
2.To avoid the direct contact of R/F with ground.
3.To save the water absorbtion from concrete which is necessary for heat of hydration.

Is This Answer Correct ?    4 Yes 0 No

why we do pcc.?..

Answer / jainender

pcc doing far leveling he is protect mud and earth, dust ect

Is This Answer Correct ?    1 Yes 1 No

why we do pcc.?..

Answer / vignesh vicky

Not using for reinforcement

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

In block work seawalls what is the purpose of slip joints?

0 Answers  


how did find the quantity of cement ,sand , and aggregate in concreat which is givan by volume

2 Answers  


How much is the cover for slab?

0 Answers  


In case of a beam ,main steel is provided along the longer span because, bending moment is directly proportional to length but why in case of one way slab main steel is provided along shorter span while as bending takes place along longer span?comment

5 Answers   Power Grid,


8. What do you find more useful in your present work – your education or your practical experience from previous jobs or traineeships?

4 Answers  






Is density and unit weight are same, if not why both r having same unit, wats the difference between them.

3 Answers  


How will you determine the capacity of a reservoir with help of contur

3 Answers   Triveni,


How many no of bricks in 4.5 inch wall per m3 If brick size is 9"x4"x2 3/4"?? Please

2 Answers   AR Rahman Foundation,


What in bending moment, if a moment is free end of cantilever beam?

0 Answers  


I am doing a engineering contract with GOI. I have purchased certain material from outside Maharashtra and paid CST on that material @ 5.25%. Please intimate whether I will be liable for VAT or VAT on works contract or not.

0 Answers   MES,


where we provide hinged joint in a framee structure ?

3 Answers  


What is bending moment

2 Answers   Skyline Builders,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)