What is the procedure of Waterproofing in toilet sunken area ?

Answers were Sorted based on User's Feedback



What is the procedure of Waterproofing in toilet sunken area ?..

Answer / bimal chettri.

First The Sunken is slab to be cleared from all loose
materials and it is to be coated with SIKA/Dr. FIxit water
proofing liquid. After that 1:2 CM plastering is to be done
and then the remaining area is to be filled with brick bats
and after that 4" PCC (1:1.5:3) is to be done with 10mm down
aggregate and after that Tiles work can be carried out.

Is This Answer Correct ?    16 Yes 2 No

What is the procedure of Waterproofing in toilet sunken area ?..

Answer / haider

First to be clean surface properly than apply two coat of tepcrit & protection plaster after fill. By light weight filling material. After that to be done PCC. Over that.

Is This Answer Correct ?    6 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.

0 Answers  


Given a selection of 28 day cube test results for concrete placed of design mix C 35 and not all of which are greater then 35 MPa, how does one decide if the concrete in place is satisfactory. Are there a minimum number of cubes that need to be tested to decide that?

2 Answers   RPS,


May I Get an E-mail ID or contact details of Mr. C.M.Dordi Vice President - Technical Sales Ambuja Cements Limited. Please

0 Answers   Ambuja, ATS,


Why do we use steel in Column? Why HYSD bar is preferable than plain bar?

11 Answers   Enercon,


what is mc arther pile?

0 Answers  






what is the difference between weir and a barrage

12 Answers   AAI Airports Authority Of India, CIT, TCI Constructions,


What are the advantages and disadvantages of Solid blocks over clay bricks in civil constructions ?

1 Answers  


afe or not

0 Answers  


what is permissible IRC limits of silt content in river sand in India

3 Answers  


factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard

0 Answers  


What is plasticiser and where it will use?

2 Answers   Simplex,


How to compute minimum number of columns required for a site from area of site?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5084)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16631)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1094)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)