what is the percentage of binding wire required for 1 mt of
steel binding in gerally

Answers were Sorted based on User's Feedback



what is the percentage of binding wire required for 1 mt of steel binding in gerally ..

Answer / er.bishnu pasad mohapatra

approx.10kg/mt

Is This Answer Correct ?    1 Yes 0 No

what is the percentage of binding wire required for 1 mt of steel binding in gerally ..

Answer / satya.mvvs

In bridges wastage is very less, so 8 to 9Kgs (.8% to .9%)
may be preferred.

Is This Answer Correct ?    1 Yes 1 No

what is the percentage of binding wire required for 1 mt of steel binding in gerally ..

Answer / babu lal nayak

thumb rool is 3 kg. bracing wires requre for 100 kg. steel.....

Is This Answer Correct ?    0 Yes 1 No

what is the percentage of binding wire required for 1 mt of steel binding in gerally ..

Answer / vishal r

9 to 11 Kg

Is This Answer Correct ?    0 Yes 2 No

what is the percentage of binding wire required for 1 mt of steel binding in gerally ..

Answer / shlender kumar

it may be 8 to 10 kg

Is This Answer Correct ?    0 Yes 2 No

Post New Answer

More Civil Engineering Interview Questions

Forces in a Shear Wall are in plane or out of plane ?

0 Answers  


Journal entry Gross salary 10000 Tax 1000 Employee contribution 2000 Employer contribution 2000

0 Answers   Accurate Engineers,


What is the yield of 100 litres of water and 10 kg of cement in grout mix?

0 Answers   NHPC,


How do you calculate load bearing capacity of a waffle slab?

0 Answers  


Brick work how many days curing and at any concreting pl

5 Answers   IVRCL,






what is the minimum and maximum water cement ratio

6 Answers  


Can fly ash bricks can be used in brick bat coba?

1 Answers  


Plz tell me...column and wall section drawing.

1 Answers  


this is jagdesh from vizag, IM GOING 2 ATTEND BHEL interview on 14th dec. im a civil engg. graduate. plzz let me know the pattern & few questions of the interview if possible. plz reply at jd_marc@yahoo.com

0 Answers  


In Residential home construct footing,beam, column,lintel,rcc roofs which dia rod used how to self assumed

0 Answers   AG Technologies,


Stander Size of Brick

11 Answers   Unitech,


how to calculate the lap bar for bor culvert ?

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)