How to calculate u.p.s load parsentage plz give me formula



How to calculate u.p.s load parsentage plz give me formula..

Answer / thangapattu

Befour we should note down the full load of current (rated
current value) Ex-400kva UBS =105A/630a*100
where
105A=currentValue in particular time
630A= Rated Current Value For UBS
= 16% is the percentage load Of UBS

Is This Answer Correct ?    4 Yes 1 No

Post New Answer

More Electrical Engineering Interview Questions

Approach of a cooling tower is the difference between temperatures of what factors?

0 Answers   Blue Star,


how can get electrical c licence.now i am working in spining mill , transformer capacity 2750KVA. SANCTION DEMAND 2250KVA. PLEASE ADVISE ME . MY CONTACT NO 09944226823

0 Answers  


why in an industry; machine having rated 200 h.p stopped after power factor is maintained above 0.97 lag by control panel in view-of energy saving

0 Answers   HCL,


WANTCONTACT NUMBER & EMAIL/ WEBSITE TO CONTACT THE SECRETARY,MADHYA PRADESH LICENSING BOARD(ELECTRICAL),K- BLOCK,3RD FLOOR,SATPOODA BHAWAN,BHOPAL

0 Answers  


what is the difference between skin effect

0 Answers  






why gravels is used in transformer yard?

6 Answers  


What is the difference between Generator Differential Relay and Transformer Differential Relay?

0 Answers  


How to find Cable size? Caterpillar generator produce (Two generators) 127*2=254 amp at 11 kv . What would be the cable size (XLPE) to supply 256 amp at 11 kv? Air or surrounding Temperature is 32 degree C. Cable will go under ground at 2.5 feet depth. Group Rating Factors is 3 cables. Clearance between cables is 7 cm. Soil Temperature (Ambient) 28o C Soil Thermal Resistivity is 1.2 K.m/W I would like to use 3 separate single core instead of using 3 core cable. Some says I should use three separate single core 120RM cables. Some says 70RM .some says 95. I m totally confused. Is there ant specific rule to determine cable size? What would be the LT cable size to flow 500 Amp current? Ifte My e mail address is ifte13@yahoo.com Anyone please send me the answer to my e mail address, i will be very glad.

1 Answers  


If single phase voltage level is 230V than why three phase voltage level is not 660V ?, but it is only 440V.

16 Answers   BSNL, DOS, EFS, HMT, L&T, TCS, ThyssenKrupp,


50 electric bulbs are connected across supply of 220 volts. After one bulb is fused remaining 49 bulbs are again connected to same supply. which case will have more illumination & WHY????????

5 Answers   KJ,


Generally in AC we consider voltage, frequency and phase sequence for parallel operation ... Can we parallel two DC battery chargers? If yes, then what precaution to be taken when we parallel two DC power?

5 Answers   Reliance,


A transformer is used to light a 24volts,70watts lamp from a 240a.c main.The current in the main cable is 0.35A. Calculate, (1) The efficiency of the transformer. (2) the current in the lamp.

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)