what is the stripping time of beam column & slab?
Answers were Sorted based on User's Feedback
For Beams sides only 1 day
For coloumns 1 day
For slabs span<4.50m 7 days
For slabs span>4.50m 14 days
Is This Answer Correct ? | 14 Yes | 0 No |
how to do cementicious paint for rcc walls of cw pump house
how the calculation occurs if i want to mix 1cum of M50 concrete. please calculate every ingredients with detail calculation.
How much sand for a 107sqm residensial building
1 Answers Shapoorji Pallonji Group(SPCL),
The horizontal distance between parallel main reinforcements in RC slab shall not be more than
1 Answers BEL, BSL, L&T, Mrkr Constructions,
what is MIS (related to planning tools)
What are the important hardware systems used for cad?
how many reputations of ply wood for concrete works can be used?
Hi how r u ? hope you are fine there . Please can u tell me tha Design life of Buildings as Per ACI CODE 318-99. It will be a pleasure for me .Thanks in advance
Define What is unit weight of normal concrete?
is load combination is necessary in staad pro design
Difference between pre-tensioning and post-tensioning.
what are the duties of Site Engineer in work site?
0 Answers Amarprakash Developers,