Answer Posted / karunakaran
For Beams sides only 1 day
For coloumns 1 day
For slabs span<4.50m 7 days
For slabs span>4.50m 14 days
| Is This Answer Correct ? | 14 Yes | 0 No |
Post New Answer View All Answers
How much qty of stone ; sand; cement in R/R stone masonry of 136 CUM
I need to constructive work in amaraj batteries
what is project?
Why joints are provided?
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.
Technical Question of Civil Engineering
Define Who designed the city of Washington DC?
Why concrete barriers have curved surface profiles?
how to calculate quantity of cement,sand & aggregate for u.c.r / r.r masonry in cm 1:6
what is m30 in concrete tiles
What is the outturn of Ceiling plastering
which software is better for design and analysis of buildings (stadd pro ) or (Etabs)
What is Time period of a building and its relation with frequency ?
The 4 main factors to start a construction project are––
How do you calculate reinforcement weight of steel?