what is the out turn of one masson in plastering, masonary
work in 8 hours, with limited healper?
what is the out turn of corpender in form work? wood work?
in 8 hour with limited healper?
what is the out turn of bar bendarin 8 hour with limited
healper for slabs, beams, coloumn?
Answer Posted / ravi
1)150to180Sft or14 to 16 Smt 2)formwork 600Sft of roof
shutering
or 112 Sft of plain door shutering
3)slab 1200Sft
beem 1.2 Ton
column 1.3 Ton
| Is This Answer Correct ? | 11 Yes | 7 No |
Post New Answer View All Answers
what is mean by c32/40s concrete class
how to calculate testing date
what might be the problem faced in the near future if the M-sand is used in the place of river sand during wall plastering? (As per IS)
What is an ice dam sock?
What are the problems one might face while having a Cantilever balcony?
what is the use of beam end forces while using a staad ? wha they are show
What is the difference between EPC,DBOOT and BOOT.
Define What is a projection line?
Does VDF add strength to the flooring apart from preventing water ingress?
What is the general specifications of a bituminous pavement road?
what r the precaution for high in atp tempareture,low in atp tempareture
Ratio for 4500 psi concrete
how to caluclate sienerge qty in construction in ap
HOw much % of premium on DSR-2013 currently
What is the significance of cost estimate knowledge for an architect?