what is the out turn of one masson in plastering, masonary
work in 8 hours, with limited healper?
what is the out turn of corpender in form work? wood work?
in 8 hour with limited healper?
what is the out turn of bar bendarin 8 hour with limited
healper for slabs, beams, coloumn?
Answer Posted / ravi
1)150to180Sft or14 to 16 Smt 2)formwork 600Sft of roof
shutering
or 112 Sft of plain door shutering
3)slab 1200Sft
beem 1.2 Ton
column 1.3 Ton
Is This Answer Correct ? | 11 Yes | 7 No |
Post New Answer View All Answers
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations
) Design a gussetted base for a column section consisting of one sc 250 with two cover plates 300 x 25 mm carrying an axial load of 2500 KN. The S.B.C. of soil is 250 KN/m2 and the permissible bearing pressure on concrete is 4000 KN.
What is the distance between railway tracks?
50 acre of land to be reclaimed for an average height of 2.5 mt. Dredging area is 500mx200m size. what is the dredging depth required to reclaim the area?
which method is used in semi-rigid connection design??
what is high type road and low type roads
how many time use of plywood shuttering and IS code
Moisture content calculation for diff mix ratio's ??
what is smart building materials?
what are the duties of Site Engineer in work site?
please send me bhel questions on rupesh.017@rediffmail.com
How to arrive dry volume of concrete (1.52 to 1.57) ?
What are the RISKS during the project construction?
acceptance criteria for concrete works
What are the methods of measurement? Describe it shortly