Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how to calculate the current if i know power in MW and
voltage 11kv/415v and also want to know that incoming
cables for trnsformer

Answers were Sorted based on User's Feedback



how to calculate the current if i know power in MW and voltage 11kv/415v and also want to know tha..

Answer / sripellirajukumar

hi this is rajkumar...
as per my knowledge
the primary side current can be calculate as follows
for example
we have power transformer of 5MW transformer and the 33\11kv
the primary current is (5000kv/33kv)/1.732=87.47amps
the secondary current is (5000kv/11kv)/1.732=262.43amps
here 1.732 is square root of 3....

Is This Answer Correct ?    43 Yes 18 No

how to calculate the current if i know power in MW and voltage 11kv/415v and also want to know tha..

Answer / cfanez

Girish,since the power is in MW,it means that we are looking
for current in consideration of power factor.If it were in
MVA,then the calculation given by Rajkumar is ideal.
5000kW=1.732*11*Ip*PF (assume pf =0.85)
5000=1.732*11*Ip*0.85
primary current Ip=308.7A
5000=1.732*.415*Is*0.85
Secondary currentIs=8,183.6A
Select cable capable from your table.If surface then
alluminum cable should be selected,if underground,suitable
hV cable should be selected to suit the primary and
secondary current carrying capacities respectively.

Is This Answer Correct ?    15 Yes 6 No

how to calculate the current if i know power in MW and voltage 11kv/415v and also want to know tha..

Answer / tasawar abbas

power factor panel calculation?
why I use the PFI panel in industry?
whose I select the kvar rating?

Is This Answer Correct ?    6 Yes 4 No

how to calculate the current if i know power in MW and voltage 11kv/415v and also want to know tha..

Answer / j.kesavan

check tr current in name plate py side after slect h.t
(xlpe)cable fix .

Is This Answer Correct ?    2 Yes 2 No

how to calculate the current if i know power in MW and voltage 11kv/415v and also want to know tha..

Answer / hosam

33000KV/11000KV 20MVA = 20000KVAX0.8=16000KW

1000kva H.V=52.5
L.V=1333.4
433V

Is This Answer Correct ?    2 Yes 2 No

how to calculate the current if i know power in MW and voltage 11kv/415v and also want to know tha..

Answer / perumalsamy o

5mva
I = 5000/33*1.732
I = 57.5A (HT amps 33 kv side)
 I = 5000/11*1.732
   =262.5A(HT amps 11kv side)

Is This Answer Correct ?    1 Yes 9 No

Post New Answer

More Electrical Engineering Interview Questions

How to calculate the cable size (XLPE)for suitable to 120KW load (if Motor or heaters etc)

4 Answers   SSC,


what is the diffrence between single phase and three phase

6 Answers  


i want to know how to calculate the battery capacity based on the UPS . ex i want to run have one kva UPS Which should run 10 hours ? in that case how many batteries to be installed and what will be the AH Value .

2 Answers  


WHY WE USE SIEMENS plC

3 Answers  


why the transformer has no starter

2 Answers   NTPC,


how to select the automotive wire size by mathematical calculation. for xenon headlamp with ballast. the ballast given data voltage 10-17v,current permenant 6amp, run up phase is 15amp, peak at swicth on max 400micro sec is 40amp.the sum of cable resistance is 150mohm.please provide referenc document if any for relating the peak at switch on current,time & wire wire size

0 Answers   Tyco,


what is the operation of UPS ? can any one answer me?

7 Answers  


how the vaccum ckt breaker workes..? how the arc is quenching in it?

1 Answers  


If the capacity of water Tank is 50000 Liters situated at 20 meters height from ground level,What would be the size of pipe and how much USGPH water will be supplied and what will be the motor or pump rating used for this work?Illustrate by showing formula?

1 Answers  


how can i increase the excitation on full load running engine??

1 Answers  


What is meant by time harmonics and space harmonics?

0 Answers  


what is the differences between microprocessor and general purpose computer

0 Answers   Stesalit,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)