In the field and in the control room different power
supplies if used How to handle the ground
Normally there should be different grounds in control room.
DCS or PLC vendor generally gives the drawing.
Mostly it is taken as convension that there should be 3
different grounding busbars in control room.
1. One is for the power earth. This will give the earthing
to the power distribution panel of the DCS or PLC.
2. Second is the Signal earth. All the shield cables will be
connected to this earthing busbar to minimize the
interference in the analog signal cables.
3. Thrd is Panel earth. This will be connected to the panel
body.
All these 3 busbars should be connected to 3 different
earthpits by 3 different Copper cables. Redundancy of
earthpits or copper cables may be there if possible.
Is This Answer Correct ? | 3 Yes | 1 No |
sir, i preparing hpcl,ongc,barc,hal exams(instrumentation engg)pls send a placement papers
Give Detail information about plc,dcs,and scada system?
Name some of the common protocol use in automation.
A flange is used for instrument connection for a system with a design temperature of 316C (600F) and a design pressure of 1000 kPa (145 psi). What is the class rating of the flange to be used for this application? Explain your answer
what is the difference between venturi and orifice meters?
What does PCU means with respect to Dead Weight Tester?
hey any one got the papers of SAIL and HPCL plz do help me by posting them to my mail ID's naren07_87@yaho.co.in, surenarendra@gmail.com
give classification of transducer based on type of application
how to convert digital signal to analog signal in plc
Explain Difference between Bech set and operating range of control valve
What is 3 element control system
what is RPI and NUT in controlnet networx. what happen if we are increase the NUT of controlnet networx?