Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


How much standard bricks required for a wall of 9*1200*1200 inches



How much standard bricks required for a wall of 9*1200*1200 inches..

Answer / biplab sinha

Vol. of wall - (9/12)x(1200/12)x(1200/12) cum = 7500 cft

1 cft = 35.28 cum so vol. of wall = 7500/35.28 cum = 212.58 cum.

For standard first class brick 1 cum = 500 nos of bricks

Therefore total bricks required = 500x212.58 nos = 106293 nos

Is This Answer Correct ?    1 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

Wats the purpose of lap length? Is it for strength or increasing of span

1 Answers  


I need to constructive work in amaraj batteries

0 Answers   Amara Raja,


how many kilograme per metre run of 6mm diameter steel bar

6 Answers  


what is the maximum number of course that can be laid according to IS code and the max height.

0 Answers  


what is the strength [final]of grade m 15 to m 45

2 Answers  


hai, kindly send anyone for output workers format details for construction project in foundation to finishing.

0 Answers  


If concrete fails in cube strength as well as non distactive test? what to do? for example grade of concrete is M35, cube strength is 26.1 n/mm2 after 28 days and non districtive test strength is 28.1 n/mm2 after 28 days. i am not distroying the rcc memeber.

3 Answers  


Providing and fixing in position Tor steel to footings, foundation, slabs, beams, columns, canopies, stair case, newels, chajjas, lintels, etc. including cutting, bending, hooking the bars, binding with wires. give me the rate M.ton.

1 Answers  


What are the delays in construction projects due to approvals from owners? How can we analyze them in different prospective? Whats their affects and effects on presently going work?

0 Answers   RealPage,


in the earthquqke the profile of water on dam is parabolic or not

0 Answers  


How Many Brick in One Cubic Meter.

9 Answers   TUV,


If the design CBR of subgrade is 10% but the material available on site is 30%.will you compact less(like 90%) where you get desirable CBR(10%).

3 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)