Answer / s k majumder
First one have to choice grade of Concrete. Say M15 grade for which proportion is 1 : 2:4. total 7
N Now dry volume will be of 1 cum concrete is 1*1.52=1.52 cum
Hence
cement= 1.52/7 = 0.217cum = 7.66cft = 6.12 bag say 6 bag
sand (1,52/7)*2 = 0.434 cum= =15.33cft
Aggregate(=1.52/7)*4 =0.868cum= =30.66cft
| Is This Answer Correct ? | 1 Yes | 1 No |
what is the difference between gypsum and pop?
What is the best mixing ratio of concrete materiloas for raft foundation?
all technical question
What's the expanded form for NMR?
1.what is the mix proportion for cement soil compressed earth blocks? 2.how to calculate the mix proportion for cement stablised earth soil blocks?
what is the measure of slump
what is the m20 grade concrete ingredients?
Describe the various methods of concrete curing?
Direct chairs over shutter / beside earth is prohibited because of ––
How to calculate cement, water, fly ash amount for 1 cum if the w/c ratio is 0.4 and fly ash to cement ratio is 1:9
How Much span required for 1 sqm of shuttering(Beam & Slab)
how many nails required in one sqm shuttering.
1 Answers BCL, Era Infra Engineering, KR Traders, Sai Foundations,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)