How to find the requirement of cement and sand for the 1cum of rr masonry work

Answer Posted / s k majumder

First one have to choice grade of Concrete. Say M15 grade for which proportion is 1 : 2:4. total 7

N Now dry volume will be of 1 cum concrete is 1*1.52=1.52 cum

Hence
cement= 1.52/7 = 0.217cum = 7.66cft = 6.12 bag say 6 bag
sand (1,52/7)*2 = 0.434 cum= =15.33cft
Aggregate(=1.52/7)*4 =0.868cum= =30.66cft

Is This Answer Correct ?    1 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to do bbs in excel format

1594


In the present situation of ban on mining sand from rivers,can we go for formation of earth dam filters viz;Horizantal sand blanket,inclined chimney and filters under rivetment with crushed rock sand of 6mm down size.If so what are the specifications and is there any codal provision for its authentication?

1497


How many Rod required for 58 feet by 24 feet roof slab which is supported by 5 * 3 = 15 Column. Six Stored building Roof Slab = ? Ton 15 Column = ? Ton Slab Beam = ? Ton

1695


it is a corrected question." make a list of engineering property(properties) of soil.

1596


Why the finite element method is lower bound solution?

2299






give me the rate analysis for Bituminous Macadam and SDBC

6938


What expenses counted in contingencies and how much it is in related to built-up area of the building.

1307


What are the different types of runners?

682


What are the different softwares used for cad?

718


As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.

1491


I'm preparing to to build a simple house, but i don't know how to calculate how much cement, gravel and sand and hollow blocks i need to prepare. How many pcs of 4" or 6" hollow blocks I need for my planned 3mx6m house? thanks. 

2323


How to calculate canal slope curvature qty!

1326


afe or not

1728


will fix foundation bolts at site with out template is there any procedure?

2157


i) Distinguish between Theodolite and dumpy Level? (Marks-8) ii)Distinguish between Viscous and Turbulent flow? (Marks-8) iii) Distinguish between nominal and design mix? iv) What is standard sand? v) Explain the term plane stress? Vi) Differentiate between principal plane and principal axis? Vii) write short notes on Elastic limit of structural steel? viii) Write short notes on stress concentration? ix) write short notes on "Grading of Sand" ? x) How many grades of concrete are there under standard concrete?

11534