How to find the requirement of cement and sand for the 1cum of rr masonry work
Answer Posted / s k majumder
First one have to choice grade of Concrete. Say M15 grade for which proportion is 1 : 2:4. total 7
N Now dry volume will be of 1 cum concrete is 1*1.52=1.52 cum
Hence
cement= 1.52/7 = 0.217cum = 7.66cft = 6.12 bag say 6 bag
sand (1,52/7)*2 = 0.434 cum= =15.33cft
Aggregate(=1.52/7)*4 =0.868cum= =30.66cft
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
what is difference between fluidity and workability also how palsticizer works
what is the meaning of 40/20 src
What expenses counted in contingencies and how much it is in related to built-up area of the building.
Process of pcc in wateredug
what is polity
i want to ecil (Electronics Corporation of India Limited Hyderabad) previous civil engineering question papers immediately please.............
What are the advantages of cad software?
I what know about life time of frp tank plz explain about it specifications & other details
acceptance criteria for concrete works
What is OSHA compliance?
For the symmetrical continuous beam shown in figure, Prestressed with a force P = 1500 KN along parabolic curve as shown, compute the extreme fiber stresses over the central support for the uniformly distributed load of 24 kn/m. Use load balancing method.
Please design 12.5m long dubbly beam
16 questions out of 55 were from the book GUPTA N GUPTA OBJECTIVE of civil engineering. Total ques were 4 ques from hydraullics, 7 from BMC, 4 FROM SOM, 4 from soil mechanics, 6 from transportation, 5 from engineering drawing.
what are the strength theories for yeilding and fracture materials. state the theory more suited for 1. mild steel or 2. concrete
sir when can we expect the AEE results and when will be the interviews sheduled please guide us in this regard thanking you