Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


How to calculate the amount of Brick,cement & sand required
for 1 cum of 115mm thick brick work with ratio 1:5 please
give me an answer with detailed step



How to calculate the amount of Brick,cement & sand required for 1 cum of 115mm thick brick work..

Answer / santosh

.240*.085*.10 = 0.00204 m3 with morter qty per brick
without morter qty of brick = .23*.075*.1 = 0.001725 m3
then 1/0.00204 = 490 bricks
= 490 * 0.001725 = 0.8456 only brick in m3
wet morter qty = 1- 0.8456 = 0.1544 m3
dry morter qty = 0.1544 * 1.32 = 0.204 m3
0.204/6*1cement = 0.03397m3 cement
cement = 0.03397 * cement density 1470/50kg per bags = 1 bags
sand 0.03397 * 6 =.204 m3 sand
sand in brass = 2.83 m3 = 1 brass 0.07208 brass

Is This Answer Correct ?    2 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

Whats the size cube

2 Answers   Shimla Hills Construction,


what opc & ppc cement $ composition?

1 Answers  


How do you change a dimension value in solidsworks?

0 Answers  


List out the diameter of series of bar for beam, column, slab and footing?

5 Answers  


Why we use pcc in foundation?

1 Answers  


how to compute slab reinforcements on step by step procedures??

1 Answers   Juniper Networks,


What is the difference between linear dimension and aligned dimension?

0 Answers  


What is Shoe Footing ?

2 Answers   Bhandari Associates,


How do we say The LAP LENGHT is 50D to 60D ?????

3 Answers  


Please provide detail I.S standard code for using crush sand instead of river sand for plaster and concrete grade M15, M20, M25 and M30 and its mix design

1 Answers   JPMorgan Chase, Sobha Developers, Structwel,


How much shuttering oil required for per m2 shuttering by 12mm ply

3 Answers  


to minimize budget cost of building , what can i do

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)