How to calculate the amount of Brick,cement & sand required
for 1 cum of 115mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer / santosh
.240*.085*.10 = 0.00204 m3 with morter qty per brick
without morter qty of brick = .23*.075*.1 = 0.001725 m3
then 1/0.00204 = 490 bricks
= 490 * 0.001725 = 0.8456 only brick in m3
wet morter qty = 1- 0.8456 = 0.1544 m3
dry morter qty = 0.1544 * 1.32 = 0.204 m3
0.204/6*1cement = 0.03397m3 cement
cement = 0.03397 * cement density 1470/50kg per bags = 1 bags
sand 0.03397 * 6 =.204 m3 sand
sand in brass = 2.83 m3 = 1 brass 0.07208 brass
| Is This Answer Correct ? | 2 Yes | 1 No |
why building got air crack? if it get in one particular are what is means?
brick size-230x110x75, how many no of bricks cover 1cubic meter.
Characteristics of a model project are ––
What letter follows after these, O, T, T, F, F, S, S, E, __?
How bonding is done for composite massonary?
2 Answers Tarmat Infrastructure,
What is the Laplenth for Reinforcement for Verticl and horizontal Structures as per IS code?
What things you need to take care of before building a kitchen island?
Explain major difference between auto level and dumpy level?
one cricket ball through in chennai and jaipur same speed where bowl has fast speed
steam curing is not used in which cement
what is the ratio of young's modulus of elasticity for a mild steel specimen in tension and compression?
what is pile foundation?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)