How to calculate the amount of Brick,cement & sand required
for 1 cum of 115mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer Posted / santosh
.240*.085*.10 = 0.00204 m3 with morter qty per brick
without morter qty of brick = .23*.075*.1 = 0.001725 m3
then 1/0.00204 = 490 bricks
= 490 * 0.001725 = 0.8456 only brick in m3
wet morter qty = 1- 0.8456 = 0.1544 m3
dry morter qty = 0.1544 * 1.32 = 0.204 m3
0.204/6*1cement = 0.03397m3 cement
cement = 0.03397 * cement density 1470/50kg per bags = 1 bags
sand 0.03397 * 6 =.204 m3 sand
sand in brass = 2.83 m3 = 1 brass 0.07208 brass
Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
What is the Unit weight of coarse sand (F.M- 2.20) ?????
For plate load test why we are applying pressure 3 times the proposed allowable bearing pressure? Is there any supporting standards for this?
How to calculate thickness of MAT slab & Reinforcement? The dimention of under ground water reservoir is 80'X14'X 12 ft
Can we use the flyash bricks in brick bat coba?
what course did you consider thinking before you enrolled in college?
I need to constructive work in amaraj batteries
For a washout valve why are two gate valves required in normal practice?
How much area will be covered in 1 litre of Velvet touch paint in normal wall condition
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?
pls tell me , what is the water content
usually hand broken stones are used for cement concrete 1:4:8 in foundation of single /two story houses with a view of economy in construction.what advantages it will give if you use machine crushed stone in place?
what is escalation?how it is done?
What are the points to be considered for calculating cement reconciliation. a)Do we need to deduct the wt of cement bags b)Do we need to adjust the qty due to wt loss during transportation, loading unloading etc or else each bag can be considered as 50 kg bag c)What is the proportion of mix cover block making.
Minimum concrete cover in slabs, columns, beams, foundation and other st?
How much permissible bearing capacity requires for open footings(isolated) and what type pile foundatuon prefering for coastal areas?