What us meant by DLP & liquidated damages in civil quantity surveying
Answer / sreekumar
DLP MEANS :DEFECTS LIABILITY PERIOD (Certificate)"
Normally it will count from the completion of the project up to 365 days as per the FIDIC. In between these period, contractor need to rectify all the maintenance and other damages. after the DLP the Consultant will be provided the Defects Liability Certificate. Then the contract can submit the Final Statement to the consultant/client for getting there 5% retention money.
| Is This Answer Correct ? | 3 Yes | 1 No |
Define unit atmospheric pressure? Difference between gauge pressure, absolute pressure?
What is meant by Anchorage length? Development Length?
it is possiblee to produce concrete with out cracks...
What is the main difference between crushing test and impact test in coarse aggregate?
how meny typs of renging rod?
What is the Tor steel Consumption for residential building G+24 footing (thum rule) ?
what is the quantity of concrete required in 1 cubic meter volume without reinforcement
List out the densities of different construction materials such as brick, steel, sand, aggregate etc...
what is the density of steel
10 Answers NGO, PWD, Sepco,
Describe a time when you anticipated potential problems and developed Preventive measures
0 Answers Graham Construction,
what are the diffrent kind of grades in concrete and what does M means while specifyng the grades?
Pls provide me with the calculation or codes related to de- shuttering of flat slabs
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)