Sir what reason the deshuttring of column 1 day after casting and slab deshuttring time 14 days after casting 

Answer Posted / rethina kumar

generally concrete is strong in compression, weak in tension, that is reason we providing reinforcement in tension zone.

1.column is compression zone, so one day is enough to deshutter
2.slab is tension zone, so it need minimum 14 days to deshutter

Is This Answer Correct ?    30 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Define the various stages of the project planning process in construction.

659


How much quantity of cement Bag for block masonry (1:4) for 1 cu.m? Block size (150x200x400) Mortar Thickness 20mm

1011


What is the quantity of cement used for stone pitching work of 100sqm 225mm thick and cement mortar of 1:6? And how?

4648


What is bylayer?

682


What is bmc stands for in bmc software?

669






what is tension footing?

1532


what is difference between fluidity and workability also how palsticizer works

6702


Dear Engineers, Can you please advise me the material requirement to construct a room 4 M x 4 M 1. No. of Standard Brick 2. Requirement of Cement Bags 3. And Concrete for Steel, Cement, sand, etc Thanks

1491


acceptance criteria for concrete works

1683


a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.

1870


What is the general specifications of a bituminous pavement road?

1235


Explain the difference between shear and tensile strength.

659


What are the standard plastic limit/liquid limit/plasticityindex for differrent type of soils?

1973


In case if concrete box girder bridges how is the number of cells determined?

709


for 32 dia (EQR HYSD steel) bar how much deduction for 45 and 90 degree band

1403