Sir what reason the deshuttring of column 1 day after casting and slab deshuttring time 14 days after casting
Answer Posted / rethina kumar
generally concrete is strong in compression, weak in tension, that is reason we providing reinforcement in tension zone.
1.column is compression zone, so one day is enough to deshutter
2.slab is tension zone, so it need minimum 14 days to deshutter
| Is This Answer Correct ? | 30 Yes | 0 No |
Post New Answer View All Answers
What will be the exam pattern and syllabus for j.e post of haryana staff selection commision? Advt no. (02/2015) Some people says it would only be objective type question papers while others say it would be same as ssc (1 objective,1 conventional) ?? Please answer this question it is needfull to all.
Define What is rigging?
please give the detail design for the soring and shuttering for 8.5m deep excavation in the sandy soil for 25x10 rectangular streaches
what is the mix design for M:60 with micro silica andmetakaoline?
Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire
What are the composition of a landfill?
How to calculate woden area in sft and Cft
Explain what is progress payment?
How do you measure water flowing through 300mm diameter pipes?
What applicable rate of wct in bihar
What is progress payment?
How to design staircase.plz tell me formula for the design the staircase.
Can we apply curing compound on ceiling (slab Bottom)
What are the advantages of cad?
Explain major differences between routing maintenance and major maintenance.