Answer / dipak rakibe
TO DERIVE THE QUANTITY OF INGREADIENT MATERIAL FOR 1 CUBIC METER OF CONCRETE FOR M-15 GRADE
Proportion for M-15 Concrete is 1:2:4
For Easy Calculations Take/Assume 10 Cu. m. of concrete.
Proportion
10 X 1.52 = 15.2
(Here 1.52 is the dry volume factor)
A) Quantity of Cement =
For 10 cum of concrete
(1/ 1+2+4)= 0.143 X 15.2 = 2.17 Cum
1 Bag of Cement = 35 Liters = 0.035
Quantity of Cement Bags = 2.17/.035 = 62.10 Bags
for 1 cum of concrete = 6.21 Bags
B) Quantity of Fine Aggregates/Sand
For 10 cum of concrete
(2/ 1+2+4)=0.285 X 15.2=4.33 Cum
Quantity of Sand = 4.33 Cum
for 1 cum of concrete = 0.43 Cum
C) Quantity of Coarse Aggregates/ Gitti
For 10 cum of concrete
(4/ 1+2+4)= 0.571 X 15.2 = 8.68 Cum
Quantity of Gitti = 8.68 Cum
for 1 cum of concrete = 0.87 Cum
Summary =
A) Cement Bags= 6.210 Bags
B) Fine Agg./Sand=0.43 Cum
C) Coarse Agg./Gitti = 0.87 Cum
BY Dipak Rakibe
| Is This Answer Correct ? | 9 Yes | 1 No |
1 cum of 1:1:4 concrete
Dry volume equal is 1.52
Cement equal is 1/6*28.8*1.52 =7.2 bags cements
= 364.8 kg cements
| Is This Answer Correct ? | 0 Yes | 3 No |
Given a selection of 28 day cube test results for concrete placed of design mix C 35 and not all of which are greater then 35 MPa, how does one decide if the concrete in place is satisfactory. Are there a minimum number of cubes that need to be tested to decide that?
What all are important things keep in mind while designing and executing the water storage tank works?
how the take measurement at column and beam junction
How to calculate strirubs hook length? one of my friend said unit of steel*dia of steel*no of bend=hook length is correct r wronge
if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete
how to calculate the steel for rcc slab 1100 Square feet
1.what is the main responsibilites of Site Engineer ? and what are main attitude ?
12 mm dia not available at site for raft, 10 mm are available at site how to calculate?
For the calculation of bearing pressure below the footing, to know whether it is below the safe bearing pressure of the soil, the unit of RCC below ground level to be taken is 25 KN/m3 or (25-15)KN/m3, where 25 is the unit weight of RCC and 15 is the unit weight of soil and whether the weight of backfilling to be taken?
which size of box use of cement,sand,aggregate to use the m 20 concrete. i know the quantity of material cement 400 kg or 8 beg ,662 kg sand and 1200 kg aggregate. i can use only 1 beg cement so pls give me answer . thx in advance
How Mney Layers in 8mm plywood
Whether dry volume or wet volume of concrete more but why?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)