If planned effort and actual effort is same, then how to
calculate the effort variance ??



If planned effort and actual effort is same, then how to calculate the effort variance ??..

Answer / saha

Effort Variance would be zero (actual-estimated)/estimated

Is This Answer Correct ?    3 Yes 0 No

Post New Answer

More Manual Testing Interview Questions

What is diffrence between the functional and black box testing.

4 Answers  


What kind of test cases are need to be included in the database migration testing?

1 Answers  


what is the FURRRPSC model?

2 Answers   CTS,


Is thr any standard format for Test Case ID like... TC_applicationname_deveopername_date_modulenumber or else we can give any ID which is unique entire the application?? plz clear my doubt...

2 Answers  


te found one bug and reported to developer or test lead after that he rejected my bug so on which basis he can reject my bug

6 Answers  






Give an example of high severity and low priority bug?

2 Answers  


I Have 2 Yrs Experience in Manual I appiled in Job Portals still i m not getting any calls plz help me wat i need to do guide me please ?

1 Answers  


Hello everybody, How many people do you think one sprint team can have in average?

0 Answers  


difference between bug reporting and bg tracking

4 Answers  


Diff b/n UAT & IST? What is meant by UAT?

4 Answers  


What are the diff types of integration testing?

3 Answers   Tech Mahindra,


How do you review testcase?? Type of Review...

2 Answers  


Categories