Answer / kalpesh g patel
Commissioning is the process of assuring that all systems and components of a building or industrial plant are designed, installed, tested, operated, and maintained according to the operational requirements of the owner or final client. A commissioning process may be applied not only to new projects but also to existing units and systems subject to expansion, renovation or revamping.
In practice, the commissioning process comprises the integrated application of a set of engineering techniques and procedure to check, inspect and test every operational component of the project, from individual function, such as instrument and equipment, up to complex amalgamations such as modules, subsystems and systems.
Commissioning activities, in the broader sense, are applicable to all phases of the project, from the basic and detailed design, procurement, construction and assembly, until the final handover of the unit to the owner, including sometimes an assisted operation phase.
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / kalpesh g patel
Commissioning is the start up of the equipment for the first time. It is when you run the equipment and carry out tests to verify it is running as intended i.e. to design specifications. Commissioning tests are normally run against a design data baseline. Commissioning also includes things like checking oil levels, fluid levels, temperatures, pressures and for general issues that are contradictory to the intended correct operation of the equipment.
Is This Answer Correct ? | 0 Yes | 0 No |
how to convert MA in to measuring values..and how mwasuring values into MA ?..plz ansr.i have intervw
what is the difference about HART, and 4-20mA signal?
what is input and output cards of plc needs to be hot swappable mean
Can anyone explain in a simple way the difference between DCS and PLC?
diff bw range and span?
use of split range ? where it is used ? in which control loop it is used ?
we callculat main steam flow by D.P. but where is H.P. & L.P. IN Orfics?
while stroke checking of a linear control valve ,found its travel is in non linear ,what can be possible reason ? ( please answer send in mannanali65@gmail.com) pls pls pls if any body know
i have level transmitter -400 to 0 range for steam drum application but i am unable to calibrate if installation of lt below lower tap what will be the effect ? and as per std wht is location of lt ,above lower tapping or below
Define cryogenic?
Can we use mov instead of esdv Explain the reason
What is the deffernce bet. Instrumentation and Electrical Enginerring?