Dear pankaj,
pl check the cross section details of the beam, if effective depth of beam is 500:
then add (500 + 150) effective depth of beam and slab thickness.
column height: 3.0 - (0.5+.15) = 2.35 M
if you find total dept of beam in cross section as 500
then :
column height: 3.0 - 0.50 = 2.50 M
| Is This Answer Correct ? | 16 Yes | 1 No |
Answer / vipin m
3ooo-500-150=2350..since at beam level reinforcement bars
has to be provided
| Is This Answer Correct ? | 1 Yes | 9 No |
what is the wait of cement in different concrete mixes from M15 TO M50
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
how much difference we have to provide when column steel staggered
who to calculate the bar bending schedule?
where is dolpin pile is used
3 Answers IGCAR, Sekar Construction, Soba,
father of soil mechanics
How and where are aqueducts built?
The compressing strength of concrete samples (cubic)
#include<stdio.h> main() { int a=300,b,c; if(a>=400) b=300; c=200; printf("\n%d%d",b,c);
what is singly & doubly rc beam? what is difference between them?
discuss the precautions to be taken during the various steps of manufacturing of concrete
150mm bricks size how many use 4.14 m3
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)