What is the Steel bar spacing formula for Concrete Slab?

Answers were Sorted based on User's Feedback



What is the Steel bar spacing formula for Concrete Slab?..

Answer / prashant

it is depend upon the type of bar(like10mm bar,8mm bar)
SPACING=((area of one bar)*(width))/(area of rienforcement calculated)
where,
width=generally 1000mm,
area of reinforcement is calculated from design load,
and area of one bar is calculated from dai of bar which we havw taken(usually 10mm and 8mm fro slab)

Is This Answer Correct ?    105 Yes 18 No

What is the Steel bar spacing formula for Concrete Slab?..

Answer / omar

(Area of steel-required- /1000) = (Area of one steel bar/S)

find S

then:
the answer will be ΦX/ each S

Is This Answer Correct ?    19 Yes 7 No

What is the Steel bar spacing formula for Concrete Slab?..

Answer / babu

Depends upon structural drawings, minimum 6" square gap

Is This Answer Correct ?    21 Yes 24 No

What is the Steel bar spacing formula for Concrete Slab?..

Answer / somnath deore

IT IS DEPENDS UPON THE SPAN.FOR LONG SPAN, SPACING WILL BE
6"& FOR SHORT SPAN SPACING WILL BE 7" TO 8".

Is This Answer Correct ?    13 Yes 16 No

Post New Answer

More Civil Engineering Interview Questions

Can anyone give me the thumb rule for calculating the time required for construction based on quantity of concrete, Reinforcement, shuttering, etc

0 Answers  


How many Steel used in 1 cum tower foundation

0 Answers   STCS,


20 mpa what is the quantity of cement sand and aggregate in one cubic meter of pcc non rainforcement concreate kindly answer including formaula thanks

0 Answers  


How much does it cost for a R.C.C cover slab of size (450mmX 600mmx 100mm) double rf net given in feets using hand mix concrete?

0 Answers   ADK,


Difference between Ghol , Chimney & fly ash bricks b)Floor to floor height is 3m , rise=15cm , tread 20 cm , how to design staircase means steps landing

1 Answers  






What the approval that owner will give to contractor during construction project period? What will the affect on project if delays due approvals?

2 Answers  


How many number of cement bags per running metre are required to cast pileof M-20 grade

1 Answers   Mantena,


Why are steel plates inserted inside bearings in elastomeric bearing?

0 Answers   Bechtel,


How many bricks required for 1 cu.m

7 Answers   Navayuga,


what is the heart of civil engineering

12 Answers   Ramky,


How much steel needed for 1 m3 concrete for slab?

5 Answers  


What is the strength of normal brick in india

3 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)