Answer / suganya
To limit the starting current we are using starters. In
motors the voltage equation is, v=Ia.Ra + Eb. At the time of
starting no back emf will be there i.e Eb=0. therfore
v=Ia.Ra since the resistance is negligible v=Ia i.e armature
current will be equal to the supplied voltage and speed will
be high. so to limit this current we are going for starters.
Is This Answer Correct ? | 12 Yes | 0 No |
Answer / chandu
for giving protection to the motor
from overloads and adjusting the
speed of the motor. now a
days,starters are replaced by drives
for automatic control.there are
various types of starters.
Is This Answer Correct ? | 9 Yes | 1 No |
Answer / bhabanipattanayak
Starter is mainly used for
limiting the high starting
current to a safe value. It is
also provide with different
equipment to protect the
motor from overload & low
voltage.
Is This Answer Correct ? | 6 Yes | 0 No |
Answer / devender kumar
for giving the starting torque to the motor.
Is This Answer Correct ? | 1 Yes | 4 No |
Answer / pradyumna chandra panda
for smooth control and provide trip system....
Is This Answer Correct ? | 1 Yes | 7 No |
Does dry and oil transformers both require dedicated neutral, because in my project we are using 2500kv dry star delta transformer, where they say neutral not required and even it is not provided in our substation. can u let me know
why 15 kw motor winding resistance is low then 5 kw motor winding resistance?
How to decide CT & PT ratings for a given transmission line carrying some rated voltage?
Do any one know exacatly when the results for NHPC held on 8th march 09 for engineering trainees will be released ?. if so please post it, i'm eager to know it.
george phenomenon of synchronous machine
please give me all the Alarm .Trip ,Safety Relays & Conditions of Diesel-generators mail me on ashokbabunhce@gmail.com
why we use MV panels??? what's r all the needs
What are the earth resistance Standards of 66kv sub stations according to indian norms.
Why in power plant projects we see DOL starting method used for motors upto 160 kW instead of star delta method
what is difference between VAT & CST
how to read AWG n how to convert AWG reading into mm?
why+ve is earthed in electrostatic precipitator in thermal power plant