what is the different betweem expansion and construction joints
Answers were Sorted based on User's Feedback
Answer / amirthalingam from ariyalur
Expansion ( Isolation) Joints:
Joint provided to take care of weathering effect & uneven
settlement in the building. Both vertical movement &
Horizontal movementIt Helps to minimize the cracks in the
building.
Construction joints:
Construction joints provided at the end of day in
a concreting where the concreting is not able to complete
in the same day. The joint provided normally 1/3rd from the
completed side span of the building (Beams, Slabs). Columns
does not require construction joints. Construction joints
is the joint between two successive placement of concrete.
Is This Answer Correct ? | 21 Yes | 2 No |
Construction joints . Construction joints are provided to
separate the areas of concrete placed at different times,
and may be
either longitudinal or transverse, as required .
(1) The spacing of longitudinal construction joints will
depend largely on the paving equipment . With most present-
day equipment, paving lanes 24 feet or more in width are
possible and may be used . Determination of the width of
paving lane to be used, that is, whether a 24-foot-wide
road or street should be paved in a single lane or in
two 12-foot-wide lanes, is left to the judgment of the
designer .
(2) When a longitudinal construction joint is used at the
center of two-lane pavements, a keyed joint with tie bars
similar to those required for longitudinal contraction
joints, or threaded split 5/8-inch tie bolt, should be
used . When a longitudinal construction joint is used at
the center of pavements having four or more paving
lanes, a doweled joint should be used .
(3) Transverse construction joints should be installed at
the end of each day's paving operation, and at other points
within a paving lane where the placing of concrete is
discontinued a sufficient length of time for the concrete
to start to set . All transverse construction joints in
nonreinforced rigid pavements should be of the doweled type,
and should be located in place of other regularly spaced
transverse joints . When paving is resumed, the regular
transverse joint construction should be used, beginning
with the first regularly Scheduled transverse joint . When
a transverse construction joint is required within a slab
in a reinforced rigid pavement, the reinforcing
steel should be carried through the joint and tie bars
added .
Expansion joints . Expansion joints are provided for the
relief of forces resulting from thermal expansion of the
pavement, and to permit unrestrained differential
horizontal movement of adjoining pavements and/or
structures . There are two types of expansion joints,
doweled and thickened-edge, both of which should be
provided with a nonextruding type filler metal . Usually a
preformed filler 3/4-inch thick will be adequate . The
expansion joint should be so designed as to provide a
complete and uniform separation between the rigid
pavements or between the rigid pavement and the structure
concerned .
1) Doweled expansion joints should be used for all
transverseexpansion joints within rigid pavements except at
the intersections of rigid pavements with structures or
with other rigid pavements . The designer is cautioned that
expansion joints within rigid pavements are difficult to
construct and maintain, and often contribute to pavement
failures . For these reasons, their use should be kept to
the absolute minimum necessary to prevent excessive
stresses or distortion in the pavement . Internal expansion
joints should be omitted in all rigid pavements 8 inches or
more in thickness, and also in pavements less than 8 inches
thick when the concrete is placed during warm weather .
Is This Answer Correct ? | 2 Yes | 2 No |
explain kn/sqm in detail.
What is the l/d ratio of cantilever beam?
In a beam tension is always at the bottom but sometimes when we design using staad we get more number of rebars at the top compression zone Why?
what is the function of fineness modulus to determine the concrete mix?
Two way slab, curtailment provided in both side in longside and short side. which side curtailment provided in one way slab?
How to find weight of steel in kg if we know the area which is in m2? Following details are known to us, Area=125m² thk of slab=250mm Steel details:T12@200 PS:considering mesh top and bottom with X and Y direction
03. a. The water cement ratio for achieving maximum strength of concrete is…… 1 b. Water/ cement is inversely proportional to-------------- 1 c. Increasing the slump decreases the strength: True / false 1
What"s mean by water bound macadam road(WBM)?
how i get all type of short type question answer about civil engg
what is the cut length for Fe 500?
How much overlapping required for welding the reinforcement bars in Columns & beams
what is a civil enggineer ?