1.how to calculate the nails qty in shuttering of column,beam, shear wall.
2.how control the binding wire wastage in building project.
3.
Answer / ratheesh
.750grms to 1Kg nails for 1sqm shuttering.
u can use single binding wires
| Is This Answer Correct ? | 2 Yes | 2 No |
What is the Roll of Water Bonding under VDF road?
what is parametre for M25 after 7 days strength
how to calculate the quantity of plaster.
what is the standard size of brick available in site in mm
what is steel
what is the density of concrete & steel? where we are using pycnometer? what is bulking of sand? what is under reinforced & over reinforced? what is balanced section?
In a slab where does the Uniformly Distributed Load (UDL) act?
how to calculate bearing capacity of soil
6 Answers L&T, Reliance, Sujala Infrastructure, TATA,
what would be compressive strength of cube for 7 days if design mix of M15
Define what is quality...
how can i calculate pcc and rcc cu.mtr rate? specify labor and material cost should be diff
how much steel and concrete required for 450 sft slab? tell also the method
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)