how to replace 8mm bar with 10mm bar if the the 8mm bar is not available..???
Answers were Sorted based on User's Feedback
Answer / mustafa mohammed layeak
Area of 8mm dia bar = 50.28 sqmm .
Area of 10mm dia bar= 78.57 sqmm .
For example if you don't have 8mm dia bar available to use
in 1m strip of slab,then one can use 10mm dia bar with an
increased spacing relative to 8mm dia bar.And reqired area
of steel in 1m wide strip is 452 sqmm/m length (Ast/m
length). the calculation is as follows
Using 8mm dia bar we get spacing in 1m wide strip as
s=[(b*Abar)/Ast] therefore s=[(1000*50.28)/452]. Therefore
required spacing with 8mm dia bars= 111 mm c/c.
similarly the required spacing using 10mm dia bars will be
spacing = [(1000*78.57)/452]. Therefore required spacing
using 10mm dia bars = 173mm c/c in 1m wide strip length.
| Is This Answer Correct ? | 63 Yes | 9 No |
Answer / murali
dia^2/spacing=dia^2/X
if there is 10mm rod 150 mm spacing replace 8mm
100/150=64/X
0.6666=64/X
therefore X=64/0.666
=96mm
if you provide 8mm rod spacing should 96mm
| Is This Answer Correct ? | 27 Yes | 4 No |
Answer / subhasis1991
You can think this in other way...
To use 10mm dia bars you just need to calculate spacing to be provided.....
When you are to use 8mm bar you would be provided the spacing(S1)..Now the spacing to be provided for a design is dependent on bar area(which is proportional to bar dia^2)...For greater bar area spacing would be less and vice versa ,so spacing is pretty much inversely proportional to the area of bar...Now to get 10mm bar spacing you just need to calculate :S1*(10^2/8^2) and you are done..
| Is This Answer Correct ? | 20 Yes | 10 No |
How to calculate the number of reinforcing bars in a slab
6 Answers Aldowin Industries, NBCC, THDC,
where bitumen emulsion is used
I want to construct 1850 square ft of rcc apartment , with stilth parking , the site requires 18 ft of pile foundation , the apartment will be above ground parking , can some one guide me about the cost of construction of such structure in Pune ?
Please tell me the quantity of cement, sand, flyash, foaming agent required for 1 cubic meter of cellular lightweight concrete blocks. also , is there any admixtures required for the CLC blocks production.
how to determine the foundation footing reinforcement spacing
what is defenation the rolling margine ? .. what is % for steel & what its effects if it is + or - ?
indiploma civil engineering student r studied is456-1978. but in practicial we r using 2000 version i think 1978 version didn't use the student. any openion?
how much quantity of bending wire required for 1sqmts
practically where this hinge and roller condition used
which beam has more strength rectangular or circular
List out some of the checking’s, done at the completion of construction?
what is the difference between weir and a barrage
12 Answers AAI Airports Authority Of India, CIT, TCI Constructions,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)