What is the difference in Line PT & Bus PT.
Answers were Sorted based on User's Feedback
Answer / antaratara ghosh
Line PT is connected in the incomer (line) to detect the
voltage of the incomer whereas bus PT is connected in the
bus, 1 before the bus coupler and another after bus
coupler, to detect voltage in the bus.
The main purpose of both of them is to sense the voltage so
that the breaker can get enough information to operate..
| Is This Answer Correct ? | 54 Yes | 1 No |
Answer / maloy
line pt is connected in incomer where the bus pt is connectd in the main bus bar though both funtioning the same for measurement & protection
| Is This Answer Correct ? | 18 Yes | 0 No |
Answer / muhammad abid ali shah
Line PT is used to measured the voltage and also used for voltage protection means that under voltage or over voltage and the bus PT is used for metering and measure the voltage of bus bar voltage.
| Is This Answer Correct ? | 4 Yes | 7 No |
What is the difference between amorphous core transformer and CRGO core transformer?.
WHAT IS THE WINDING PROCEDURE OF ELECTRICAL MOTOR
specific gravity of a battery?
which type of capacitors using in single phase motors
I WANT TO KNOW LONGFORM OF CT/PT USEDIN POWER PROJECTS OR HT SWITCH YARD.
How can we calculate the motor frame sizes?
Why iron core losses are constant at all loads in a transformer ?
what happens if i connect acapacitor to a generator load
why in a transformer frequency remains constant? if frequency is changing what will happen?
according to ohms law ,the voltage increases then current is what happened?
Please clarify, 1. Is it required to lay two runs of GI wire along with Armoured LT cable if it is laid between one big mains (63Amps TPN SDF) to small main (32A TPN SDF) with proper glanding termination? 2. If the armoured cable with proper glanding is laid from DB to CNC machine, is it required to run two runs of body earthing to the Machine from DB? 3.If the armoured cable with proper glanding is laid from Substation to Hangar, distance is approx. 100 mtrs, is it required to do earthing at shop area though the primary termination at substation is earthed through gland.
What are the essential parts of a transformer?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)