calculate qty of sand in 15 mm plaster for 100 sqm.
Answers were Sorted based on User's Feedback
wet mortar =100*.015=1.5
dry mortar =1.5*1.2 =1.8
ratio =1:4 (assumed)
sum =1+4=5
sand =4*1.8/5=1.44 cu m (answer)
| Is This Answer Correct ? | 32 Yes | 7 No |
Answer / kumar navneet
Unit- 1sqm ; take 100sqm
Qty of mortar req to plaster wall= 100sqm x .015m=1.5cum
To make up for uneveness inc by 30% = 1.5+ (1.5x30)/100= 1.95cum
Inc by 25% the total dry volume = 1.95+ (1.95x30)/100
= 2.34 cum
for 1:4 cement sand mortar (Assumed)
Cement = 2.34/(1+4)= 0.468cum
Sand = 0.468 x 4= 1.872cum
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / qaisar imtiaz
15MM PLASTER FOR 100 SQ.M
THEN TOTAL AREA IS MEAN 10*10=100 SQ.M
10*10*0.015=1.5 CUM
RATIO =1:3
FOR CEMENT =1.5/4*1=0.375/0.0354=10.60 BEG
FOR SAND = 1.5/4*3=1.125CUM
| Is This Answer Correct ? | 1 Yes | 2 No |
Answer / er. shivam dixit
15 mm plaster for 100 sq. m.
then the total quantity = 1500 cu. m.
let us consider the cement plaster proportion is 1:4
then the total sum of the proportion = 5
total dry mortar required for 1cu. m. = 0.40
the sand required for one cu. m. = (4*0.40)/5 = 0.32 cu. m.
so the total sand required 15mm plaster for 100 sq.m.
= 15*100*0.32 = 480 Cu.m.
| Is This Answer Correct ? | 2 Yes | 36 No |
if a 1 storey building is constructed without columns&beams and having the thickness of walls 12" in which cement&sand mortar is used what is the lifespan of building
0 Answers Ryna Facilities Services,
for pretensioning which will yield first and same for post tensioning?
What is the maximum allowable wastage in pouring of Ready Mix Concrete received at location with transit mixtures. Work scope includes both Direct Pouring & manual pouring.
1 Answers AKM Construction Management,
What are the causes of building collapse?
briefly describe your ideal job?
What is labor and material payment bond?
How to calculate the crank length of the rod in beam? Please give me a details.
what is the crushing strength of stone and bricks?
2 Answers DFCCIL, FWO, Habib Group, HBL, KPSC Kerala Public Service Commission, Mott MacDonald,
What is mean by uniaxial bending
DEFINE M30 GRADE CONCRETE. FROM THIS QUESTION WHAT; "M" & 30?
7 Answers Descon, Northstar Homes,
How much steel required in one cubic meter RCC Main girder
How much steel required for only ground floor of 1600 Sq foot.Having general structure ?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)