Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

calculate qty of sand in 15 mm plaster for 100 sqm.

Answer Posted / er. shivam dixit

15 mm plaster for 100 sq. m.
then the total quantity = 1500 cu. m.
let us consider the cement plaster proportion is 1:4
then the total sum of the proportion = 5
total dry mortar required for 1cu. m. = 0.40
the sand required for one cu. m. = (4*0.40)/5 = 0.32 cu. m.
so the total sand required 15mm plaster for 100 sq.m.
= 15*100*0.32 = 480 Cu.m.

Is This Answer Correct ?    2 Yes 36 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the meaning of Brick- M 35 grade? Is it a common brick or it's a concrete brick?

1885


I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

2084


what is cement wastage percentage in NHAI ROAD WORKS

1882


Concrete cover for slab, column, beam and footing?

1085


how to take the quantity of block work and plastering  1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate

2460


How to calculate cement and river sand material Qty for waterproofing base coat and finish coat

2403


Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.

2616


Define What is diversion tunnel in a dam?

1244


What is change order request?

1087


Required concret Surface Temperature prior to coating of epoxy pain with references ASTM or ACI whatever

2244


In a beam,stirrups are placed closely at ends than at centre due to shear.similarly where would ties be closer to each other-at center or at ends in a column and slab.

3314


What in your past experience or education prepares you for the position for which you are applying

2208


Define What is the origin of name Railway Sleepers?

1275


If specific gravity of cement is less than 3.15 what is the cause?

2306


If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?

1825