concrete strength process timing is 1 year
after 28 days concrete gets 90% strength
then
for - M15=1:2:4=15+1.5=16.5 n/mm^2
for - M20=1:1.5:3=20+2=22 n/mm^2
for - M25=1:1:2=25+2.5=27.5 n/mm^2
& above the m25 grade,that is Based on design mix per IS.
for find strength of above m25 grade strength=concrete strength after 28 days+10%strength of concrete getting strength after 28 days
getting m45 grade strength laboratry test used
ther generally cement ratio increased & test & test till geting m45 strength
Is This Answer Correct ? | 5 Yes | 2 No |
Answer / goutam giri
It gains 100% strength after full curing (fully immersed in water)
Is This Answer Correct ? | 1 Yes | 0 No |
W mm mix rasio
what is lap length? why it is required?
how to reduce size of column 450 x 750 to 230 x.... if it is cut in area of bathroom? means it appears in bathroon any shifting or any other option....building is g + 10 and the bathroom is at first floor...
Types of pile, which should be prefer in sandy soil
what is mean by "SQP"
how much shuttering oil required for 100 sqm shuttering?
Sir what reason the deshuttring of column 1 day after casting and slab deshuttring time 14 days after casting
define the engineering property of a soil. make a list of list property(properties)
2 Answers AAI Airports Authority Of India,
Explain the term 'Gross unit rate' and identify the items that may be included in the gross unit rate.
why we used bricks in brickbat coba? main roll of bricks ? how it function?
3 Answers Brigade, Waskom Construction,
M.C.Q
3 Answers Mitsui OSK Lines, TechInfini,
How much cost is required for 1 Flyash Brick?