how 1.52 factor comes while calculating no of bags of
cement...from 1:2:4 design mix?
Answers were Sorted based on User's Feedback
Answer / ajay kumar singh
For 100cum of finished concrete =152cum dry volume of
conc. Hence for 1cum the factor will be 1.52
Calculation of material in 1cum of (1:2:4)conc.
Cement=1.52/1+2+4=0.217cum
Sand=0.217*2=0.434cum
Metal=0.217*4=0.868cum
Is This Answer Correct ? | 63 Yes | 6 No |
Answer / a.jagadesh
For 100cum of finished concrete =152cum dry volume of
conc. Hence for 1cum the factor will be 1.52
Ratio = 1:2:4 For 1m3
= total ingredients = 7
= For cement 1/7x1.52 = 0.217 m3
= For sand 2/7x1.52 = 0.434 m3
= For 20 mm 4/7x1.52 = 0.868 m3
----------
= 1.519 m3 = 1.52 m3
----------
Is This Answer Correct ? | 20 Yes | 6 No |
Answer / er.balasundari
This 52 means dry volume to be considered always 50-55%. We can choose those 52 r 53 r 54. Bt mstly choose 52%.Hence it is 1m3 + 52%= 1+0.52 = 1.52. This s very crct answer.
Is This Answer Correct ? | 4 Yes | 1 No |
Answer / sravan
both the above explanations are correct which give the same result!!!
Is This Answer Correct ? | 1 Yes | 0 No |
What is the difference between a wood shake and wood shingles?
Specific gravity of Cement? Water?
how much bags of cement will be in 1 cmt of having the ratio 1:3:6
what is the minimum % of steel use in columns ?
what is the cost of per cum of pile foundation?
tmt steel
density of flyash
At one time what is the height of Lift for concreting for Bridge Piers Class B Loading and refer the code.
Management diagram of your project isβββ
How to calculate volume of dry mix concrete?
What is need for setting limits?
how to calculate total cost for slab 35'×8'