When brick size is 3x5x9" , what would be the number of
Brick requirement for 100 sqft area of 5" width?
Answers were Sorted based on User's Feedback
Answer / sohag vyas
Total quantity of wall = 14400 x 5 (14400 conveted into
sq.inches)= 72000 cu.inches.
volume of one brick= 3x5x9=135 cu.inches
hence no.of bricks reqd.= 72000/135= 533 nos.
Is This Answer Correct ? | 7 Yes | 2 No |
Answer / abdullah
In 100 s1 ft there are 100 sq ft x 12 x12/ 3 x 9sq inch = 533 no of bricks of size 3x5x9 inches the width of wall being 5 inch
add 5 % for wastage = 26.65
559.65no say say 560 pcs
Is This Answer Correct ? | 3 Yes | 1 No |
Answer / vijayakumar.s
Total volume/volume of one brick(with morter thicknes)
Is This Answer Correct ? | 1 Yes | 2 No |
Answer / n alam
total area=100 given and width is also given=5" so tota
l area=10*12*10*12*5=72000 sq inch and vol of bricks =3*12+5*12+9=105 so no of require bricks =total area/vol of bricks =72000/105 =685.71 bricks
Is This Answer Correct ? | 0 Yes | 1 No |
Respected sir i am appearing for the exam this year.I will be highly obliged if u kindly send me last year's interview paper on civil engineering in my email address debosmitroy@yahoo.in
WHAT IS THE MAIN DIFFERENCE B/W HIGHWAYS AND MOTERWAYS?
how can u extent the final setting time of cement?
3 Answers TNPSC Tamil Nadu Public Service Commission,
what is the Purpose of Adding 20% of wet mortar & 1/3rd to Dry Mortar for PCC & Plastering & Rcc .is there any standard method for adding this .?
How to rectify thermal cracks (2mm wide, 9mm deep aprx. ) developed in tremix finished concrete floor?
How to calculate unit conversion area
Can anybody explain with the help of sketeches that what are 2legged , four legged & 6legged stirrups and how to calculate cut length of diamond ring(stirrups)?
HOw many cement bags are required for M35, M40 & M45 grade of concrete?
Define the various stages of the project planning process in construction.
Cut Linten (RCC-1:2:4)on 10" wall - what should be the width and hight of cut Linten? Secondly, 1 X 1.6 foot,4" thick window sun/rain shed (Chajja)should consume steel,Cement, sand and Stone chips?
what is the actual productivity of carpentor,fitter,masson for brickwork and masson for plaster etc
What out turn civil works