Should vertical shuttering done for CC/ RCC for Damp Proof
Course (DPC) be measured?
Answers were Sorted based on User's Feedback
Answer / r.k sharma
IS code 456-2000 states that Forms shall not be released until
the concrete has achieved a strength of at least twice the
stress to which the concrete may be subjected at the time of
removal of formwork (para 11.3).Minimum Period Before Striking
Vertical formwork to columns, walls, beams is 16-24 hours.
CC/RCC for DPC on plinth is never subject to any stress and
meant for retaining the material till Cement sets.As such it
should not be measured separately and treated as incidental to
the Work of DPC.
Is This Answer Correct ? | 6 Yes | 0 No |
Answer / anupom
Above answer is right, also
THe thickness of DPC is very less(apprx. 25mm) and is
generally applied as a coating layer for plinth level. Thus
the vertical shuttering may not be measured but this solely
depends on the contract specification.
Is This Answer Correct ? | 3 Yes | 0 No |
shearing strength of cohesionless soil depends upon dry density rate of loading confining pressure all above
Why we are using coarse sand for brick work and is there any technical problem if, we use fine sand instead of coarse sand.
what is mean of buld density
what are the stress act on circular slab?
pls tell me , what is the density of cement when normal packed
A person becomes tired when ups a stairs because of––
deshuttering time for RCC wall & column
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
there is a residential building L = 20' B = 30' H = 20' stairs L = 3' H = 20' calculate the numbers of Threads and risers from stairs with formula
how many bricks in 1 one cubic meter?
What is differnce between founadation & footin ?
How may digree of freedon in four bar chain.