Should vertical shuttering done for CC/ RCC for Damp Proof
Course (DPC) be measured?
Answer Posted / r.k sharma
IS code 456-2000 states that Forms shall not be released until
the concrete has achieved a strength of at least twice the
stress to which the concrete may be subjected at the time of
removal of formwork (para 11.3).Minimum Period Before Striking
Vertical formwork to columns, walls, beams is 16-24 hours.
CC/RCC for DPC on plinth is never subject to any stress and
meant for retaining the material till Cement sets.As such it
should not be measured separately and treated as incidental to
the Work of DPC.
Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
Which are the top apps for you civil engineer?
What are the different types of civil engineering?
How to build the floor to ceiling bookcase?
Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.
what is civil enginnering & what you need of this course?
Explain what are the problems one might face while having a Cantilever balcony?
What is the cemnent ratio
how to caluclate sienerge qty in construction in ap
five benefits of using standard terminology in the measurement process
For plate load test why we are applying pressure 3 times the proposed allowable bearing pressure? Is there any supporting standards for this?
What is unit weight of roadway layer.. 1.bitumen 2.sand 3.soil 4.concrete 5. aggregate give me some reference for this answers
What is meant by cartesian coordinate system?
How will you Engage Labours on Site?
What is the difference between the concrete mix design carried out by IS10262 and by ACI method ?
How many bricks are there in 100cft?