Should vertical shuttering done for CC/ RCC for Damp Proof
Course (DPC) be measured?
Answer Posted / r.k sharma
IS code 456-2000 states that Forms shall not be released until
the concrete has achieved a strength of at least twice the
stress to which the concrete may be subjected at the time of
removal of formwork (para 11.3).Minimum Period Before Striking
Vertical formwork to columns, walls, beams is 16-24 hours.
CC/RCC for DPC on plinth is never subject to any stress and
meant for retaining the material till Cement sets.As such it
should not be measured separately and treated as incidental to
the Work of DPC.
| Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
How will you Engage Labours on Site?
Process of pcc in wateredug
please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.
How can I make justification between using concrete grade c35 compare c37?
hi, i am appearing in HPCL(CIVIL ENGG.)exam. plz send me placement paper of this exam if u are having
can you provide a link for manual design of building?
How much qty of stone ; sand; cement in R/R stone masonry of 136 CUM
What are the uses of layer?
Which IS Code/American Code applied for coupler test of steel
Explain the term 'Gross unit rate' and identify the items that may be included in the gross unit rate.
importance of the soundness test to determine the quality of cement use for any construction
What is c.g.i sheet which used for roof??
though u r a civil engineer, y r u interested in tcs???
what is castigliano theaorem
what is column foundation