Should vertical shuttering done for CC/ RCC for Damp Proof
Course (DPC) be measured?
Answer Posted / anupom
Above answer is right, also
THe thickness of DPC is very less(apprx. 25mm) and is
generally applied as a coating layer for plinth level. Thus
the vertical shuttering may not be measured but this solely
depends on the contract specification.
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
What are the ingredients of pre-stressed concrete?
How much cement and water required for cement selery????
How much quantity water should be placed in one cubic meter area?
how to find the cement bags and sand requirements for the one square meter of internal,external,ceiling plastering by using the various ratios like 1:3,1:4,1:5,1:6
could u tell me how to used deform stell bar in reinforce concret?i wanna know the general using in the site!
Method of findingthe dry ingredient quantity of 1 m3 concrete. what is the difference between static and dynamic induced emf? Testing charges bill given for Rs. 32,000/- but not added service tax in this bill. So, How much TDS will be deduct
how do we calculate quantity of cement sand and aggregates in 1m3 of m20 m25 grade concrete?
what is difference between fluidity and workability also how palsticizer works
What is meaning of tlc
Define Who designed the city of Washington DC?
How much time Required for PPR pipe network testing
What are the common ways of demolition?
Is it worthwhile to carry out tests on particle density of soil particles for geotechnical design?
What is fineness modulus ? and its sieve # ?
Required concret Surface Temperature prior to coating of epoxy pain with references ASTM or ACI whatever