Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what is periode of deshuttering of slab our span length
21m,and width 2.5m grade of concrete M-35

Answers were Sorted based on User's Feedback



what is periode of deshuttering of slab our span length 21m,and width 2.5m grade of concrete M-35..

Answer / raju msra

14 days

Is This Answer Correct ?    10 Yes 1 No

what is periode of deshuttering of slab our span length 21m,and width 2.5m grade of concrete M-35..

Answer / naresh

14 Days

Is This Answer Correct ?    2 Yes 1 No

what is periode of deshuttering of slab our span length 21m,and width 2.5m grade of concrete M-35..

Answer / sliajit dasgupta

Minimum 7 days, maximum 21 days

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

How to calcuate the quantity of cement,sand for plastering 1:4 12mm thick?

1 Answers   L&T,


if rise and tread of stairs rae 16 & 25cm with landing slab of thickness 100mm . If there are 8steps, and carpenter ask for to mark the bottom of centering of landing on column, what will be the height above floor finished level?

2 Answers  


Types of Water Proofing Material?

2 Answers  


How to calculate no of 12 mm dia bars in a ton

2 Answers   Galfar,


what is the density of the polythene sheet

2 Answers   NCC,


what is meaning of AWS Welding procedure

3 Answers  


What expenses counted in contingencies and how much it is in related to built-up area of the building.

0 Answers  


20mm thick sand face plaster on walls consisting of 12 mm the backing coat of c.m.(1:3)and 8mm thick finished coat of c.m.(1:1)including scaffolding, watering, finishing etc complete please calculator with methyl et et r u

0 Answers   Dhruv Construction,


how to calculate the load bearing capacity of slab hos thickness and steel are already given?

3 Answers  


why there is need to provide shear reinforcement?give the basic reason?

9 Answers   JMC, L&T, Power Grid,


What is cutting Length of stirrups of a beam 300mm*300mm.

3 Answers  


Is there any possibility of changing in dia of bar from lower to higher (i.e Lower dia bar at bottom and Higher dia bar at top)

3 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)