what is periode of deshuttering of slab our span length
21m,and width 2.5m grade of concrete M-35
Answer Posted / sliajit dasgupta
Minimum 7 days, maximum 21 days
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
How to calculate brick work quantity?? Block work quantity??
plz drive the formula d2/162.162 for the calculation of weight of steel bars????
How do we determine the specific gravity of a cement?
Why are steel plates inserted inside bearings in elastomeric bearing?
what is the theoritical percentage of concrete cubes testing per day?
What is factor not to be taken in consideration in mix design?
a concrete mix 1 2 4 by volume with water cement ratio as .6 by weight if moisture content in F.A is 6% with 20% BULKING AND IN C.A 1.5% by volume. find quantities of different materials required for one bag of cement
What is diversion tunnel in a dam?
how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?
how to convert cement, sand aggregate quantity from M3 to kg with full description?
manhole height is 1500 mm and width of brickwork is 230 mm dia of manhole covering is 560 mm brick masonry 1:4 horizontal length is 1500 mm and plaster 12 mm thick on both side 1:3. how to estimate the quantity of brickwork with mortar cement and sand for manhole chamber.
what is spacing of wallar support of 3m column. the thickness of column is 0.25 m.
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
How to calculate 1 brss for RCC work
Why should appointment store person for project ? what is the benefits for company ?