It can be done by following the steps below.
1. Take the control loop in manual mode.
2. Block the temperature control valve position manually to
the desired value.
3. Now check the loop as per the normal loop checking
procedure i.e. feed 4-20ma and observe the output value on
the DCS.
| Is This Answer Correct ? | 11 Yes | 0 No |
Answer / senthil.doosan@yahoo.com
simple..
there is no hot loop check or cold loop check..
as u mentioned u have a temp transmitter and control valve
so,u have 2-AI and 1-AO
-connect the simulator by removing the DCS cable of the temp
transmitter,then give 4 - 20 mA and check with DCS reading
-give 0 to 100% command from the DCS for AO to operate the
control valve.then check the feedback in the DCS(AI)
conclusion,ur loop is ok...
| Is This Answer Correct ? | 6 Yes | 2 No |
how u calibrate pneumatic n motorized c/v?
if my flow is 20000 m3/h than which range of DPT i have to use????
What is mean by ATEX?
How to measure high frequency using thermistor
wat are the interview questions asked in air india for post service engineer
1 Answers AirIndia, Shree Renuka Sugars,
What is passive connection of instrument in different types of IO module?
I have 475 hart communicator. this is not support any new type of instruments such as tranmitter,fieldvue DVC6200.DVC 200 since i got point out need to upgrade . my questions is how can upgrade new instruments software in my 475 hart communicator. can any answerplease>?
In E&I diagram what is the meaning of rectangular box and circular box
In control valve , Failure position : Close If it is Fail close(FC) during failure of AIR.. what will be the initial/ normal position of control valve is it normally open or close? please some one explain soon..
What is calibration?
How does temperature bath work? How does coil gets heated only by applying some current?
0 Answers Process Control Technologies,
how to calibate level transmiter ?range -150 to +150.what is the zero and span?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)