how to calculate the required qantities of cement, Sand and
aggrigate to prepare 1 Cum of concrete mix 1:2:4
Answers were Sorted based on User's Feedback
Answer / jayaraaj.arumugam
mix design 1:2:4; (1+2+4 = 7)
(using 20mm aggregate)
Volume of ingredients - 1.57 ( thump rule)
Aggregate - 4/7 * 1.57 = 0.89 Say 0.9 m3
sand - 2/7 * 1.57 = 0.448 say 0.45 m3
cement - 1/7 * 1.57 = 0.224 say 0.225 m3
weight of cement required - 0.225 * 1440 = 324 kg.
if any mistake please inform...
| Is This Answer Correct ? | 65 Yes | 10 No |
Answer / pritesh .c . bhoi
mix desighn = 1:2:4= 7
quantity is 1 cum add 52% westage and shreankage
so 152 cum
cement = 1*1.52/(7)=0.21714 cum (dry volume)
volume of one bag is 0.0347 cum
so no of bags are 0.21714/0.0347= 6.25 nos say7 numbers
bags are required
sand = 2*1.52/(7)=0.43428 cum
course aggregates = 4*1.52/(7)=0.86857 cum so conclution
is
cement =7 nos bags
sand =0.43428 cum
course aggregates =0.86857 cum
if any mistake please informed . thank you
| Is This Answer Correct ? | 24 Yes | 9 No |
Answer / vikas patil
For 1 Cu.m Concrete (1:2:4)
Cement =1.52/(1+2+4)=.217 Cu.m=.217/.035=6.2 Bags
Sand=(1.52*2)/7=0.434 Cu.m
Agg.=(1.52*4)/7=.86 Cu.m
out of 0.86Cu.m of Agg use following Proportion of Agg.
20mm Agg=0.65*.86=.56 Cu.m(65%of 0.86Cum)
&
10mm Agg=0.35*.86=0.3 Cu.m(35%of 0.86Cu.m)
Summary=>
Cement=6.2 Bags,
Sand=0.434 Cu.m,
20mm Agg=0.56Cu.m,
10mm Agg.=0.30Cu.m
| Is This Answer Correct ? | 1 Yes | 4 No |
Answer / raaj
Dear sir,
aggregate is more quantity required then sand, then how it is possible?
sand use in per 1 cum=27.14cft
aggrigate use in per 1 cum=13.57cft
kindly clarify i also need the answer for unit wise.
| Is This Answer Correct ? | 2 Yes | 7 No |
Answer / er.puspak kumar sahu
concrete ratio=1:2:4
area=1cum
1+52%=1.52cum(add the extra 52% for dry material)
cement=1.52/(1+2+4)=0.217cum=(0.217/0.035)=6.2bags
(per bag cement volume=0.035cum)
sand=1.52/2=0.76cum=(0.76/0.028)=27.14cft
(0.028 is a conversion factor)
aggrigate=1.52/4=0.38cum=(0.38/0.028)=13.57cft
(0.028 is a conversion factor)
finaly=
cement use in per 1 cum=6.2bags
sand use in per 1 cum=27.14cft
aggrigate use in per 1 cum=13.57cft
| Is This Answer Correct ? | 4 Yes | 11 No |
calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick
In olden days reinforcing bars in concrete are not got rusted even till now. But recently provided steel getting rusted in concrete. what are the probable reasons?
What is Current Shuttering rate (labour + materials) for Columns, Beam & Slab on Item rate basis ?
What is the life of anaerobic Digester if it is used for municipal solid waste digetion.
how to know 28 day strength of concrete knowing 3 day or 7day strength of concrete???
What is a BBS?Find out the cutting length for a 300*300 column with 40 mm cover?
21 Answers L&T, SSC,
what does the track parameter mean in staad.pro?
how to calculate estimation for puttey... give me an example
what is tmc ,term is used in measureing water, pls tell me 1 tmc = how many litres?
18 Answers College School Exams Tests, Irrigation, IT Consulting Services, IVRCL,
what is 3.14 indicates for cutting length of stirrups
state the functional requirement of a retaining wall
what is minimum reinforcement required for rcc works
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)