how to calculate the required qantities of cement, Sand and
aggrigate to prepare 1 Cum of concrete mix 1:2:4
Answers were Sorted based on User's Feedback
Answer / jayaraaj.arumugam
mix design 1:2:4; (1+2+4 = 7)
(using 20mm aggregate)
Volume of ingredients - 1.57 ( thump rule)
Aggregate - 4/7 * 1.57 = 0.89 Say 0.9 m3
sand - 2/7 * 1.57 = 0.448 say 0.45 m3
cement - 1/7 * 1.57 = 0.224 say 0.225 m3
weight of cement required - 0.225 * 1440 = 324 kg.
if any mistake please inform...
Is This Answer Correct ? | 65 Yes | 10 No |
Answer / pritesh .c . bhoi
mix desighn = 1:2:4= 7
quantity is 1 cum add 52% westage and shreankage
so 152 cum
cement = 1*1.52/(7)=0.21714 cum (dry volume)
volume of one bag is 0.0347 cum
so no of bags are 0.21714/0.0347= 6.25 nos say7 numbers
bags are required
sand = 2*1.52/(7)=0.43428 cum
course aggregates = 4*1.52/(7)=0.86857 cum so conclution
is
cement =7 nos bags
sand =0.43428 cum
course aggregates =0.86857 cum
if any mistake please informed . thank you
Is This Answer Correct ? | 24 Yes | 9 No |
Answer / vikas patil
For 1 Cu.m Concrete (1:2:4)
Cement =1.52/(1+2+4)=.217 Cu.m=.217/.035=6.2 Bags
Sand=(1.52*2)/7=0.434 Cu.m
Agg.=(1.52*4)/7=.86 Cu.m
out of 0.86Cu.m of Agg use following Proportion of Agg.
20mm Agg=0.65*.86=.56 Cu.m(65%of 0.86Cum)
&
10mm Agg=0.35*.86=0.3 Cu.m(35%of 0.86Cu.m)
Summary=>
Cement=6.2 Bags,
Sand=0.434 Cu.m,
20mm Agg=0.56Cu.m,
10mm Agg.=0.30Cu.m
Is This Answer Correct ? | 1 Yes | 4 No |
Answer / raaj
Dear sir,
aggregate is more quantity required then sand, then how it is possible?
sand use in per 1 cum=27.14cft
aggrigate use in per 1 cum=13.57cft
kindly clarify i also need the answer for unit wise.
Is This Answer Correct ? | 2 Yes | 7 No |
Answer / er.puspak kumar sahu
concrete ratio=1:2:4
area=1cum
1+52%=1.52cum(add the extra 52% for dry material)
cement=1.52/(1+2+4)=0.217cum=(0.217/0.035)=6.2bags
(per bag cement volume=0.035cum)
sand=1.52/2=0.76cum=(0.76/0.028)=27.14cft
(0.028 is a conversion factor)
aggrigate=1.52/4=0.38cum=(0.38/0.028)=13.57cft
(0.028 is a conversion factor)
finaly=
cement use in per 1 cum=6.2bags
sand use in per 1 cum=27.14cft
aggrigate use in per 1 cum=13.57cft
Is This Answer Correct ? | 4 Yes | 11 No |
Please let me know about answer for my Question as "What is the maximum wastage allowable of HYSD Steel in any Bridge project as per Code and Code reference also ?
0 Answers Amit Enterprises, ICT,
Forces in a Shear Wall are in plane or out of plane ?
What is reinforced brick masonary and its advantages and applications, arrangement of steel
strength of bitumen concrete with 80-100 & 60-70 grade bitumen
Which are the top apps for you civil engineering?
from where ican get sample papers for CET-delhi 2012
How does siphoning work?
PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.
Consumption of Binding wire for fixing of cover block in vertical surface
what is P.C.C ?
by which IS Code bend correction is two times of the dia meter of steel is taken
How to decide/consider the grade of bitumen for dbm.