What is meant by class of CT&PT?
Answer / hareesh
CTs have two fuction one is metering & othjer is protection.
for metering CT (0.1, 0.2 ,0.5,1.0 etc class).that means
error of CT has some tolerence limit. if u r using a 0.2
class CT (500/1A).at 500A ur CT error shud exceed more than
0.2%. i.e class represent some allowable limitation of
error in the ct. so CT shud not exceed this error.choosing
the type of class depends upon application. if u want more
accurate measurement u shud go for 0.1 class CT. tariff
calculation based on CT n PT reading.. if u dont have
better accuracy.. ur calculation of tariff also wont be
accurate. protection CT classes are( 5P,10P,PS etc)this
deals with CT saturation characteristics. like metering CT
this is also have some tolerence limit.thats wht we call
class
| Is This Answer Correct ? | 11 Yes | 2 No |
What is the importance of creepage distance in disc insulator ?
1.two coupled coils with L1=L2=0.6 H have a coupling coefficient of k=0.8 the turns ratio N1/N2 is......
what is inter connected dc generator?
0 Answers Lovely Professional University,
how we can calculate which capacity capacitor bank we have to add for improve pf?
3 Answers Consultancy, JM Huber, Torrent Power,
WHAT IS THE FUNCTION OF RCCB
In a 3 pin plug holder, what is the purpose of diameter of ground pin is larger than phase and nutral pin
What is the use of oil in transformers?
Does the motor power displayed on the Motor name plate is the mechnical power motor delivers or it is consumed power from the system?
WHAT IS MEANT BY TV TERMINAL IN 500MVA TRANSFORMER?
what is the opencircuit tes &short circuit test in transformers ,why you need this test, in poen your connecting which votmeter why?
why holding contact is not using in VCB and ACB breakers?
I am having a 42KW 3 phase electrical heating furnace, heating element is 80/20 nichrome material, my connections is made in such a way that 2 star connection compromising 2 coils per phase so totally 12 coils, shall if i use it unbalanced star condition (instead of 2 group of 3 phase or 1 group of 3 phase, connecting 4 phases of 5 phases) what will be the consequences and is it acceptable?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)