how to carry out Magnetizing Current Test on Distribution
transformer and what purpose we are doing this test.



how to carry out Magnetizing Current Test on Distribution transformer and what purpose we are doing..

Answer / bl meena

mag. current is tested to see whether all the 3 phases are
properly magnetised or not.If any phase is taking a higher
current then it could be said that in that phase some
conductors are short,So it's better that during this test
variac be used to apply the voltage,one should slowly
increse the voltage or just on-off the multimeter used to
see the quick response,if current is quickly incresing use
variac,to protect the multimeter.

Is This Answer Correct ?    10 Yes 5 No

Post New Answer

More Electrical Engineering Interview Questions

What is the difference between the watt hour meter and Var hour meter in terms of internal connection and work theory . ie "When the meter records watt-hour an when the meter records var hours ??"

13 Answers  


Why restricted earth fault protection is needed? Why can’t differential Protection is sufficient?

0 Answers  


Is voltage & potential transformer are the same? Are they used for same application ?

11 Answers  


why transformer comes only in standard rating like 11kv,33kv,66kv....and not like 33.33kv and so on?

3 Answers  


which type of questions asking for solar companies?

0 Answers   GE,






What is corona loss?

2 Answers   PWD,


how does it help for selection of a transformer.

0 Answers  


i have total 8 dg sets for synchronizing and 2 buscoupler,1 sectoin dg no 1,2,3,and 2 sectoin dg no 4,5,6,and last section dg no 7,8 ....if buscupler no 1 and 2 is off mode ..than dg no 1,2,3,will synchroniz of another dg sets?

0 Answers   Crown Buildtech,


relation between voltage and frequency.

5 Answers   IIUI, Lucky Cement, Reliance,


what is the use of choke on tube light fitting

37 Answers   Bhel, Dharma, HSBC, TCS,


What is the cause for a blown fuse in one phase of primery side(HV) of a three phase transformer( 4169v-460v) in the time of closing its supply breaker. There is no load on the secondery side of the transformer in this moment.

3 Answers   Novachem,


Why we use mho Relay in long transmission line?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)