In a given rcc design, how to calculate quantity of steel,
for all practical purpose of construction?
Answers were Sorted based on User's Feedback
Answer / rajendra.l.d
The question should be framed thus: "How to calculate
quantity of steel for practical purpose of construction"....
"In a given RCC design" it is simple to arrive at the
quantity by calculating the lenght of each bar & multiply
with the unit weight of given dia.
The thumb rule for calculating steel quantity is 1.5 to 2.0
Kg/Sft....
| Is This Answer Correct ? | 60 Yes | 13 No |
Answer / shalim
d x d / 162 kg/m.where d =diameter of bar in mm
| Is This Answer Correct ? | 40 Yes | 12 No |
Answer / sjtbehera
For all pratical purpose you can calculate steel by
measurment given by drg.All sreels come with their unit
weight. by calculating their respective unit weight toal
wt. can be calculated.
| Is This Answer Correct ? | 41 Yes | 15 No |
Answer / er satyavir singh kashyap
FOR FOUNDATION 50KG PER CUM
FOR SLAB 80KG PER CUM
FOR BEAM 110 KG PER CUM
FOR COLUMN 160KG PER PER CUM
FOR WALL 80 KG PER CUM
FOR SHELVES 80KG PER CUM
FOR STAIR CASE 100 KG PER CUM
| Is This Answer Correct ? | 24 Yes | 4 No |
Answer / pallavi
The quantity of steel can be calculated by formula:
d*d/162 kg/m. where d=diameter of bar in metre
this formula has been derived by relation
density=mass/volume
However, percentage of steel in rcc structure can be taken
as 0.15% of the gross area of cocrete
| Is This Answer Correct ? | 37 Yes | 20 No |
calculation for one meter is d*d/162.162 d=dia of steel (mm)
than mutiply by length of steel bar
| Is This Answer Correct ? | 13 Yes | 0 No |
Answer / azizurrehman
formula=d*d/162.162 d is Dia of steel in mm
then multiply with bars
| Is This Answer Correct ? | 4 Yes | 0 No |
Answer / adnan khan
for all practical purposes calculation of steel should be find in bar bending schedule which we can easily understand that which types of bars used and the weight different for all steel dia.
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / murali krishna r
for small scale, consider 2.5-3 kg/sft of BU area. For
commercials etc, may go up to 4.5 kg/sqft.
| Is This Answer Correct ? | 7 Yes | 6 No |
how much quantity are required like cement,sand,aggregate for (46*29*0.41)feet slab? how much this quantity can be calculated?
difference between deep and shallow well?
What is ideal location for cube casting, RMC vehical at Ground Floor and Slab casting at 40th Floor
how many nails in 1 sq mitar
WBM Road aggregates quantity calculation
Why should pumping be not used in case of concreting works?
I've beams dimensions of 9"x 18"x 45' please calculate the weight. Thanks
2 Answers SRR Properties, Student, Treetop Solutions,
what would be compressive strength of cube for 7 days if design mix of M15
Which condition will prevail for the design of a swimming pool ? When the pool is empty or when it is filled ?
for solid cement brick without fly ash,we use dust,6mm,12 mm jelly,water my question is what Proportion we mix dust,6mm,12 mm jelly,water ? for good strength brick.
what is difference between GTS bench mark and temporary bench mark
what a pigment?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)