In a given rcc design, how to calculate quantity of steel,
for all practical purpose of construction?
Answer Posted / er satyavir singh kashyap
FOR FOUNDATION 50KG PER CUM
FOR SLAB 80KG PER CUM
FOR BEAM 110 KG PER CUM
FOR COLUMN 160KG PER PER CUM
FOR WALL 80 KG PER CUM
FOR SHELVES 80KG PER CUM
FOR STAIR CASE 100 KG PER CUM
| Is This Answer Correct ? | 24 Yes | 4 No |
Post New Answer View All Answers
What are the disadvantages while using stone dust as filler in pavements?
04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1
what is yield and tensile strength of steel, if steel has yeilding strength of 60 psi than how much its tensile strength?
how much repeitation for conventional and maivan formwork?
how to calcualate the amount of stone,cement,sand required for 1cum of 450mm thick ruble stond masonary with ratio1:5, please me an answer with dtailed step
How cracks in concrete can be avoided?
What are the methods in tiles flooring ? What are the methods in brick work? What are the methods in plastering ? What are the methods in wall tiling?
The mixture of different ingredients of cement is burnt at?
1. For 10sq.m area(47 kg bitumen contain) of 45 mm thick bitumen mix layer..how much bitumen is required for 1600 sq.m and how much aggregate need for that ?? 2. And much tonnage of bitumen mix required for 10 sq.m area of 45 mm thick. Please give answer...
How can i do RCC rate analysis?
02. a. The diagonal of a 9 cube…………… 1 b. Surface area of 9 cube…………… 1 c. Volume of 1-3 cube …………… 1 d. Compressive area of 6 cube …………… 1 e. Top & Bottom face of a Cylinder/Cube is to be proper leveled to deliver the…………………………..…… properly.
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
i need gate exam civil engineering question papers with answers
may i know the detailed description of cutting length
How to calculate cement, water, fly ash amount for 1 cum if the w/c ratio is 0.4 and fly ash to cement ratio is 1:9