Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


Determine the minimum cable size for a 28A single phase
final sub circuit originating from the distribution board
supplied by three phase submain. The route length of the
final sub circuit is 54 m. Assume 1% voltage drop in the
consumer's mains. Submain specification: Cable: 50mm2 4
core V75 copper; Route length 42m; Maximum demand 135A per
phase



Determine the minimum cable size for a 28A single phase final sub circuit originating from the dis..

Answer / james santhosh lenin

3x4sqmm(phase,neutral,earth

Is This Answer Correct ?    3 Yes 2 No

Post New Answer

More Electrical Engineering Interview Questions

what could be the reason of a burnt current transformer in an electrical panel

1 Answers   ERWAT,


Can VFD step up to 60 Hz if it is designed to receive 50 Hz input?

3 Answers  


What OPGW is better than Microwave or PLCC???

0 Answers   Four Seasons,


why does voltage generation at 11 kv?

2 Answers  


Construction of ac motor?

1 Answers  


1)Explain why the cradle guard is used on railway crossing in overhead line construction?

0 Answers  


How to calculate the size of earth cable to earth the neutral of UPS ?

0 Answers   N Johnson,


What is converter transformer? Diff b/w converter transformer and distribution transformer? why we use converter transformer in place of giving supply to drives?

1 Answers  


A TRANSFORMER 440/400V,DELTA/STAR CONNECTED.THE NEUTRAL CONNECTED WITH GROUND CABLE THAT IS DIRECTLY CONNECTED TO THE PANEL,FROM PANEL IT IS CONNECTED EARTH PIT.IS IT RIGHT? IF IT IS RIGHT LEAKAGE CURRENT AFFECTED.SECONDATY IS PROTECTED WITH EARTH LEAKAGE RELAY.

0 Answers   Jindal,


For a Potential Transformer(PT), the primary neutral terminal must be grounded before energization. Why....? What will be heppend if we energize the PT without grounded the primary neutral point? Why..........?

2 Answers  


What is EHT(Abrebiation,Function,Voltage Regulation & how it works?

2 Answers   Adhunik,


How we calculate the size of ht cable for any transformer

0 Answers   WalMart,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)