Answer / ranga
take the ratio 1:1.5:3
cement =1
sand =1.5
metal =3
So what is the ratio we want to mixing 1+1.5+3=5.5
Volum of wet cement concret is 1.54 to 1.57
unit weight of cement bag is 1440 kg/cum
one bag of cement = 50/1440 = 0.034722 cum
SOLUTION : CEMENT = 1.54/5.5 =0.28
=0.28/0.0347 = 8.069 ( 8 bags)
one bag of cement =50 kg X 8.069 = 403.45 kgs.
SAND solution =0.28 X 1.5 = 0.42 Cum
1.5 is the mixing proportion
METAL SOLUTION = 0.28 x 3 = 0.84 cUM.
3 is the mixing proportion
1 Cum cement concrete is 1:1.5:3 ratio
cement = 403.45 kgs.
sand = 0.42 Cum.
metal = 0.84 Cum.
| Is This Answer Correct ? | 679 Yes | 142 No |
Answer / sachdeva d.p
M30- cement=1/4*1.54=0.385*28.8=11bags
sand-0.385*1=0.385cum
agregate 0.385*2=0.77cum
Notes;why we multiply by 1.54
dry dencity=1.54*wet denciti in conct.work
| Is This Answer Correct ? | 246 Yes | 93 No |
Answer / rajarshi basu
The approach by Sjtbehera is totally correct but has some
little silly mistakes...I have tried to give a rectified
solution.
In the case M30 design mix, the quantities of cement,sand
and aggregates cannot be calculated as it is a variable
quantity.It depends upon the Mix designer how much quantity
of cement,sand and aggregates he will employ.His only
intention would be to design a mix whose specified
characteristic compressive strength at 28 days=30 N/sq.mm
But in case of nominal mix we can use 1:1:2
Let us consider a volume of 10 cu. m (Wet concrete)
It is difficult to access exactly the amount of each
material required to produce 10 cu m of wet concrete when
deposited in place.
Hence to convert the wet volume into dry volume,
Increase by 54 % to account for shrinkage and wastage
Thus it becomes=15.4 cu. m (Variable upto 15.70)
Calculating cement, sand and aggregates in the mix:
Total summation of proportion=1+1+2=4
Cement = 15.4/4= 3.85 cu. m =3.85/0.0347=110 bags
Sand=15.4/4=3.85 cu. m
Aggregates(20mm to 6mm)=15.4 x (2/4)=7.70 cum
Hope u have understood and the mistake is clarified!!!
| Is This Answer Correct ? | 174 Yes | 65 No |
Answer / deepa
how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M7.5 grade concrete ?
| Is This Answer Correct ? | 34 Yes | 10 No |
Answer / samsulhoque@jadavpur universit
for m30 grade .we have to calculate the quantity of all
ingredients of concrete by design mix as per IS
10262-2009.it depends upon the whether admixture is used or not.
| Is This Answer Correct ? | 50 Yes | 31 No |
Answer / rahul mehta j.e
Take a Ratio 1:1.5:3
Now 1+1.5+3= 5.5
Now Divide This By 1.52 Which Is wet Volume
Now 1.52/5.5 =0.276
Now Multiply This by 30 Coz 1 Cum Of Cement Contains 30
bags dry.
==> 0.276 X 30 = 8.29 Bags Or 414 Kg cement.
| Is This Answer Correct ? | 80 Yes | 62 No |
Answer / enayatullah
Take the retio 1:1.5:3
Cement = 1
Sand = 1.5
Aggregates = 3
The volume of none mixed material is 1.52 m3 for one cu.m
mexid concret becouse the the aggregate sand and cement
have porosity that will fill with some of sand and
cement,so 1.52/(1+1.5+3)=1.52/5.5=0.276
Cement=0.276*1=0.276 cu.m = 0.276/0.036*50 bag = 383kg
0.036 is one bag volume
Sand = 0.276*1.5 = 0.414 cu.m
Aggregate = 0.276*3 = 0.828 cu.m
0.276+0.414+0.828=1.518 near to 1.52
| Is This Answer Correct ? | 45 Yes | 27 No |
Answer / subilash .s(civil engineer)
for designing 1m3 concrete of M25 mix the ratio is 1:1:2
for calculating cement,sand and course aggregate ,
cement= 1/(1+1+2)=.25
density of cement =1440kg/m3
cement required for this mix=1440*.25=360kg=6bags+10kg
sand=1/4=.25m3
course aggregate=1-.5=.5m3
this methode of designing is known as volume batching ,this
methode will be ues to design mixes upto m25.
| Is This Answer Correct ? | 86 Yes | 69 No |
How can calculate cement quantity in brick work
why +1 to be followed for calculating the no of bars in BBS. Please explain
The relation between cube strength & cylinder strength because––
what course did you consider thinking before you enrolled in college?
How many kilo of binding wire required for one ton of reinforcemet steel binding?
17 Answers ECCI, L&T, Shri Janani Homes,
a g+2 building having mezenine floor ,but stair is approching only 1st and 2nd floor, in this case stair is calculate in plinth area for mezenin floor or not?
What is binding spacing of the rebars at lapping zones.
how is the wastage component in structural steel being considered while doing the reconcillation for the fabrication with returning of scrap under 1 meter length
4 Answers LIC, NTPC, Tata Steel Limited,
what is meant by MIS report
how much cost of single coat 20mm thick plastering per sqre meter
state the functional requirement of a retaining wall
Why do we not deduct steel volume to find actual volume of concrete in practical as we have studied that,,, actual volume of concrete = volume of column- volume of steel pls explain with reference of IS code?????
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)