Answer / shailesh singh
Battey backup(va)=mah×v×n of battery/watt
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / sathiyanarayanan
backup formula= KVA/DC LOW *POWER FACTOR
FOR EX:2 KVA/120 DC VOLT(SYSTEM VOLT)OUR MAINTAINED POWER
FACTOR (0.8 P.F),PER BATTERY=12V(DC LOW=10.8),HERE USING THE
SYSTEM VOLT=120V SO,10 BATTERIES-10*12=120V
DERIVATION : 2000/108*0.8
AH=14.81(APP.17 AH BATTERY) given 30 minutes backup
Is This Answer Correct ? | 7 Yes | 8 No |
Answer / chetan singh
Battery Volt X No of Battery X Battery AH / Load in watt
Is This Answer Correct ? | 4 Yes | 5 No |
Answer / mehboob
( Battery Voltage * AH Rating * Efficiency) / VA Rating = X
X * 60 = Estimated Run Time in Minutes
So let’s pretend we’re looking at a theoretical UPS unit that has the following specs:
VA Rating: 700
Battery Voltage: 12
AH: 9
Efficiency: 0.9 (90%)
When we plug those numbers into the equation we get the following:
( 12 * 9 * 0.9 ) / 700 = 0.139
0.139 * 60 = 8.3 minutes
Is This Answer Correct ? | 0 Yes | 3 No |
what are the advantages of having high voltage in transmission lines?
How much current can 11KV line carry? What are the formulae used to calculate current across both side of transformer? Moreover I need to know can I connect 33KV line with transformer of 1600KVA? Details are: V=415, Pf= .9
We have 2 no. 4MW DG set. and GEB supply. But, we running, only 1 DG set. when we done APFC/Power factor setting : 0.90, then winding temp. Low. but when setting done : 0.83, then Winding temp. increase. WHY Why ? ? ?, plz give me answer.
What is UPS and How do you maintain the UPS Maintenance? Brief Description on UPS maintenance.
0 Answers JLL, Nokia, Uttam Galva,
why secondary of transformer always grouded?
Which type of gas used in cylinder (VCB)?????
what is a difference berween line voltage and phase voltage?
Draw the vector diagramme for Asynchronous Induction Generator at noload,half load and fullload.
If we have to feed a housing complex having load 8MVA, than what would be the better option, either we first step down 33kv supply into 11kv & than 430v or we proposed no of 33/.44 kv transformer, also which option is economical?
how we can calculate earth fault current?
at high temperature conductivity increases for conductor what will happen for long transmission when temperature is high?
which motors is used in mixies