Answer / bharath
need to go for 3, 7 & 28 days. And care to be taken in WC
ratio & Cube filling process while concrete process
| Is This Answer Correct ? | 7 Yes | 1 No |
Answer / shashank
wait till 28 days result will come some time 7 days result
will fail due to poor workmanship will pouring the cube
| Is This Answer Correct ? | 6 Yes | 1 No |
Answer / riaz
The actual result come after 28 days but it still depend on weather condition
| Is This Answer Correct ? | 2 Yes | 0 No |
Answer / ratheesh
If 7th day cube fail, we have to wait 28 day cube result.
Should be use skilled labours...then wont get any cube failure.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / mohd. haider
By checking the strength of member by core cutting or remote hammer test. If strength is OK. Than no problem otherwise take action seriously.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / amar kantak
RECHECK THE STRENGTH AND WATER , CEMENT , COARSE & FINE GRAVEL
QUALITY.
| Is This Answer Correct ? | 1 Yes | 1 No |
Answer / pk priyadarshi
in three numbers cube one number cube discard and take two numbers cubs average strength if strength is found as per required that is ok
| Is This Answer Correct ? | 0 Yes | 0 No |
7. Do you apply the skills and knowledge learnt at school in your work?
how to calculate the crushing strength of cement concrete paver blocks 100x100x60 mm thich.
what is the minimum compressive strength of clay brick
0 Answers Ananya Construction Infrastructure, VNC,
Why we are not provide bar in the centre of the column and bar?
how to calculate required shuttering material like props,spans,plates ..etc for a slab?
1 Answers NCC, Shoba Devlopers,
What is the strength of 1:6:12 mix?
Diversion of cum to cft
HOW TO FIND OUT THE QUANTITY OF CONCREATE
water cement ratio
How to find out slope footing concrete
0 Answers Ekta World, Punj Lloyd Ltd,
relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2
what is density of flyash?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)