Answer / bharath
need to go for 3, 7 & 28 days. And care to be taken in WC
ratio & Cube filling process while concrete process
Is This Answer Correct ? | 7 Yes | 1 No |
Answer / shashank
wait till 28 days result will come some time 7 days result
will fail due to poor workmanship will pouring the cube
Is This Answer Correct ? | 6 Yes | 1 No |
Answer / riaz
The actual result come after 28 days but it still depend on weather condition
Is This Answer Correct ? | 2 Yes | 0 No |
Answer / ratheesh
If 7th day cube fail, we have to wait 28 day cube result.
Should be use skilled labours...then wont get any cube failure.
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / mohd. haider
By checking the strength of member by core cutting or remote hammer test. If strength is OK. Than no problem otherwise take action seriously.
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / amar kantak
RECHECK THE STRENGTH AND WATER , CEMENT , COARSE & FINE GRAVEL
QUALITY.
Is This Answer Correct ? | 1 Yes | 1 No |
Answer / pk priyadarshi
in three numbers cube one number cube discard and take two numbers cubs average strength if strength is found as per required that is ok
Is This Answer Correct ? | 0 Yes | 0 No |
How to calculate lap,bond and hook length for preparing bar Bending schedule ?
11 Answers L&T, Saudi Aramco Shell Refinery Company SASREF, Sunil Hitech Engineers, Tempus, Zain United Arabian,
How to calculate unit conversion area
How do you find the difference between 53&43 grade cement in site?
what is the maximum number of course that can be laid according to IS code and the max height.
how to calculate the scour depth
why are you joining in this (applied post) job and your aim for this job
how many rod are needed in 99sqft room .
5 Answers Associated Construction Company,
What is a kip?
what is BPM in concrete demolition hammers. what is better a higher value or lower
at what height brick masonr, block masonry & Concrete wall can construct in a day ?
what is pmc(in rigid pavement)
what is the unit of heat of hydration?